04.12.2026

lcmd onsiteOur next webinar

Grid connection in 2031, charging park in 2027: how you bridge the gap with a storage system and still make the numbers work
Use Case

Grid-scale storage co-location: PV, green power storage system & trading BESS as a grid-supportive system

5 MWp ground-mounted PV as grid-scale storage co-location: how a green power storage system optimises PV revenues, and how a second trading BESS scales the net present value (NPV) from €563k to €3.15 million.

Use Case key data

13,5%

Return

6.5 yrs

Payback period

3.15M

Net present value (NPV)

1.14M

Revenue/year

A 5 MWp ground-mounted PV system with no self-consumption, operated purely as Direktvermarktung (selling generated power via a direct marketer under the German EEG). All power is sold via the Day-Ahead market and the market premium. Grid connection: 4,049 kW.

Scenario 1: PV only

Baseline scenario with pure PV grid feed-in. All 3,860 MWh/a are marketed without a storage system. Investment: €2,750,000. Revenue: €227,160/a. Net present value (NPV): -€337,606, return: 6.5%, payback period: 12.1 years. PV alone is barely viable, as the net present value (NPV) is negative.

Scenario 2: PV + green power storage system (10,738 kWh)

A 10.7 MWh green power storage system shifts PV power into higher-priced hours and sells it via Direktvermarktung from the storage system. The grid connection rises to 5,645 kW. Investment: €4,897,658. Revenue: €550,735/a. Net present value (NPV): €562,971, return: 9.4%, payback period: 9.2 years. The green power storage system turns the case positive.

Scenario 3: PV + green power storage system + trading BESS (22,587 kWh, fixed grid connection point)

A second, much larger trading storage system (22.6 MWh) trades power actively: Day-Ahead arbitrage and Intraday Continuous arbitrage. The grid connection point limit keeps the grid connection at 4,049 kW. Investment: €7,267,356. Revenue: €1,143,989/a. Net present value (NPV): €3,146,295, return: 13.5%, payback period: 6.5 years.

Result

The step from scenario 2 to 3 shows the leverage of active power trading: with €2.4 million of additional investment, the net present value (NPV) rises by €2.58 million, and the trading BESS pays for itself through arbitrage revenue. The grid connection point limit keeps the grid connection constant and avoids costly grid expansion. minimum.energy models both storage systems as one co-location system in a single run.

Sign up once and stay informed

What our customers calculate with it.

Commercial roof with 99 kWp: EEG 2027 calculated with feed-in limit and market premium

Model calculation for a commercial business with 500 MWh consumption and 99 kWp PV, under current law and under the draft EEG 2027. Because the business consumes 87% of its PV power itself, the feed-in limit barely changes the result. With a market premium, the benefit of the storage system rises by 10%.

87 %

Self-consumption rate of the PV system

0,3 %

of generation lies above the feed-in limit

19,2 %

Return on storage system with market premium (today 15.7%)

5.0 years

Payback period with market premium (today 6.0)
View Use Case →

20 MWp solar park: redispatch reservation calculated with and without a green electricity storage system

Model calculation for a 20 MWp solar park in the other Direktvermarktung (selling generated power via a direct marketer under the German EEG), under current law and with the redispatch reservation from the draft grid package. Without storage, the internal rate of return falls from 7.0 to 5.4%. With a green electricity storage system, it falls from 9.1 to 8.7%.

5,4 %

Rate of return without storage (today 7.0%)

2.5 GWh

additionally curtailed per year

60 %

of the revenue loss is offset by the storage system

8,7 %

Rate of return with storage (today 9.1%)
View Use Case →

AgNes capacity charge: what happens to the peak shaving calculation from 2029

Same site, same storage system, new grid fee system: the value contribution from peak shaving falls from €19,602/a to minus €4,258/a. The return falls from 11.8 to around 7 per cent.

11,8%

Return until 2028

7,3%

Return from 2029

-100%

Value contribution from peak shaving

43.5k

Additional costs p.a. from AgNes
View Use Case →

MiSpeL BTM with three stakeholders: The free grid connection as a business case

The site has a 750 kW grid connection and uses 413.7 kW of it. How a BESS investor uses the free 336 kW in line with MiSpeL, and what is left for the site and the direct marketer.

12,8%

Investor IRR

-44%

Site operating costs

103k

Total benefit per year

336 kW

Free grid connection
View Use Case →

C&I (commercial and industrial): one storage system, all revenues. The same storage system with and without MiSpeL

A commercial site with 750 kWp of PV is assessing a 2 MWh storage system. The same storage system, calculated twice: with full grid fees and levies on the trading electricity, and MiSpeL-compliant. The net present value (NPV) rises from €287,000 to €762,000.

132k

Savings/year (previously 80k)

762k

NPV (previously 287k)

3.8 yrs

Payback period (previously 6.3)

2,7×

NPV through MiSpeL
View Use Case →

From PPA to energy contracting: how the contract model decides the battery business case

Same site, same PV, but depending on the contract model, the business case ends up almost 10× larger. And the best part: the investor earns, the consumer saves, with no CAPEX of their own.

22,2%

Return

4.8 yrs

Payback period

7.59M

Net present value

-33%

Ongoing costs
View Use Case →