Grid connection in 2031, charging park in 2027: how you bridge the gap with a storage system and still make the numbers work
Use Case

Convert a diesel fleet to e-trucks: BESS avoids grid expansion

Convert a diesel fleet to e-trucks without upgrading the grid connection: how a 229 kWh BESS makes the expansion unnecessary, and dynamic power purchasing drives the return to 30%.

Use Case key data

30,3%

Return

3.4 yrs

Payback period

-64%

Operating costs

-43%

CO₂ emissions

A logistics site in Bochum runs a diesel fleet with an annual fuel consumption of 2,347 MWh diesel/a and a grid connection of 368.4 kW (Bochum municipal utilities). The goal: full conversion to e-trucks without costly grid expansion.

Methodology

In minimum energy, five scenarios were modelled and compared directly, from the status quo to the fully integrated solution with storage, dynamic tariff and PV.

1. Existing | Diesel fleet (status quo)
Baseline: 1,187 MWh/a electricity demand, 2,347 MWh/a diesel. Operating costs: €1,192,737/year, emissions: 1,104,000 kg CO₂/year.

2. Switch to e-vehicles (without storage)
The grid connection is not sufficient. It has to be upgraded to 414.9 kW. Investment: €2,500,000. Operating costs: €525,814/year (-56%). Payback period: 3.7 years, return: 27.8%/year.

3. E-vehicles + grid connection limiting (229.6 kWh BESS)
Battery storage limits the grid connection power, so the grid connection stays at 368.4 kW, no expansion needed. Investment: €2,565,788. Operating costs: €524,552/year (-56%). Payback period: 3.8 years, return: 27.1%/year.

4. E-vehicles + grid connection limiting + dynamic power purchasing (302.8 kWh BESS)
The storage system is also used for Day-Ahead arbitrage, and the optimal storage size rises to 302.8 kWh. Investment: €2,586,284. Operating costs: €435,024/year (-64%). Payback period: 3.4 years, return: 30.3%/year. This is the economic optimum.

5. E-vehicles + dyn. power purchasing + PV (204.5 kWh BESS + 750 kWp)
PV complements the system: self-sufficiency 35%, self-consumption 92%, electricity sales 51 MWh/a. Investment: €3,046,254. Operating costs: €360,314/year (-70%). Payback period: 3.6 years, return: 28.2%/year. CO₂ emissions: -43% to 630,000 kg/year.

Result

The key lever: A 229.6 kWh storage system (grid connection limiting) makes the grid connection upgrade unnecessary, at almost identical costs to the scenario without storage. If you also integrate dynamic power purchasing, you reach the economic optimum: payback period of 3.4 years, return of 30.3%/year.

The case shows: Fleet conversion without storage sizing is incomplete. minimum energy calculates all scenarios in minutes, with real grid fees, real load profiles and real capital expenditure.

Sign up once and stay informed

Here is how you can calculate it:

What our customers calculate with it.

Commercial roof with 99 kWp: EEG 2027 calculated with feed-in limit and market premium

Model calculation for a commercial business with 500 MWh consumption and 99 kWp PV, under current law and under the draft EEG 2027. Because the business consumes 87% of its PV power itself, the feed-in limit barely changes the result. With a market premium, the benefit of the storage system rises by 10%.

87 %

Self-consumption rate of the PV system

0,3 %

of generation lies above the feed-in limit

19,2 %

Return on storage system with market premium (today 15.7%)

5.0 years

Payback period with market premium (today 6.0)
View Use Case →

20 MWp solar park: redispatch reservation calculated with and without a green electricity storage system

Model calculation for a 20 MWp solar park in the other Direktvermarktung (selling generated power via a direct marketer under the German EEG), under current law and with the redispatch reservation from the draft grid package. Without storage, the internal rate of return falls from 7.0 to 5.4%. With a green electricity storage system, it falls from 9.1 to 8.7%.

5,4 %

Rate of return without storage (today 7.0%)

2.5 GWh

additionally curtailed per year

60 %

of the revenue loss is offset by the storage system

8,7 %

Rate of return with storage (today 9.1%)
View Use Case →

AgNes capacity charge: what happens to the peak shaving calculation from 2029

Same site, same storage system, new grid fee system: the value contribution from peak shaving falls from €19,602/a to minus €4,258/a. The return falls from 11.8 to around 7 per cent.

11,8%

Return until 2028

7,3%

Return from 2029

-100%

Value contribution from peak shaving

43.5k

Additional costs p.a. from AgNes
View Use Case →

MiSpeL BTM with three stakeholders: The free grid connection as a business case

The site has a 750 kW grid connection and uses 413.7 kW of it. How a BESS investor uses the free 336 kW in line with MiSpeL, and what is left for the site and the direct marketer.

12,8%

Investor IRR

-44%

Site operating costs

103k

Total benefit per year

336 kW

Free grid connection
View Use Case →

C&I (commercial and industrial): one storage system, all revenues. The same storage system with and without MiSpeL

A commercial site with 750 kWp of PV is assessing a 2 MWh storage system. The same storage system, calculated twice: with full grid fees and levies on the trading electricity, and MiSpeL-compliant. The net present value (NPV) rises from €287,000 to €762,000.

132k

Savings/year (previously 80k)

762k

NPV (previously 287k)

3.8 yrs

Payback period (previously 6.3)

2,7×

NPV through MiSpeL
View Use Case →

From PPA to energy contracting: how the contract model decides the battery business case

Same site, same PV, but depending on the contract model, the business case ends up almost 10× larger. And the best part: the investor earns, the consumer saves, with no CAPEX of their own.

22,2%

Return

4.8 yrs

Payback period

7.59M

Net present value

-33%

Ongoing costs
View Use Case →