04.12.2026

lcmd onsiteOur next webinar

Grid connection in 2031, charging park in 2027: how you bridge the gap with a storage system and still make the numbers work
Use Case

From PPA to energy contracting: how the contract model decides the battery business case

Same site, same PV, but depending on the contract model, the business case ends up almost 10× larger. And the best part: the investor earns, the consumer saves, with no CAPEX of their own.

Use Case key data

22,2%

Return

4.8 yrs

Payback period

7.59M

Net present value

-33%

Ongoing costs

Starting point

An industrial site buys electricity through a conventional on-site PPA with a 2,300 kWp PV system. Electricity demand: 14,889 MWh/a. Ongoing energy costs: €2.87 million/a. The question: is a battery storage system worthwhile, and under which contract model?

Scenario 1: Battery without a new contract

Within the existing PPA structure, only a small storage system (2,843 kWh) can be justified. From a project perspective: €798k net present value (NPV), 19.4% return, payback period of 5.0 years. Split across the stakeholders, the investor keeps €529k (15.6% IRR) and the consumer only €269k. Both share a small pie, because the contract structure caps the added value.

Scenario 2: Battery under energy contracting/tolling

As soon as the battery is structured as an energy contracting/tolling model, everything changes: a storage system 6× larger (17,833 kWh) becomes economically viable. From a project perspective: €7.59 million NPV at a 22.2% return and a 4.8-year payback period. The split is what matters: the investor carries the investment of €4.99 million and achieves €2.24 million NPV at 13.2% IRR. The consumer contributes no capital of their own (no CAPEX, no risk) and still gains €5.35 million NPV through lower energy costs. Almost ten times the project value, and both sides are better off than before.

Scenario 3: Battery and full supply

With a full supply model, the storage system grows larger again (20,156 kWh). From a project perspective: €8.43 million NPV, 22.2% return, 4.8-year payback period. The investor achieves €2.21 million NPV (12.6% IRR), and the consumer increases their benefit to €6.23 million, still without a single euro of CAPEX.

The key point: a win-win for both sides

Without a new contract, investor and consumer share a small pie. With the right energy contracting model, the pie becomes almost 10× larger, and both get more: the investor a solid investment with a double-digit IRR, the consumer substantial savings without any CAPEX.

Result

The hardware is not the lever, the contract model is. Conventional tools only calculate the overall system. minimum energy shows what reaches each individual stakeholder, which is what makes negotiations workable in the first place.

Sign up once and stay informed

What our customers calculate with it.

Commercial roof with 99 kWp: EEG 2027 calculated with feed-in limit and market premium

Model calculation for a commercial business with 500 MWh consumption and 99 kWp PV, under current law and under the draft EEG 2027. Because the business consumes 87% of its PV power itself, the feed-in limit barely changes the result. With a market premium, the benefit of the storage system rises by 10%.

87 %

Self-consumption rate of the PV system

0,3 %

of generation lies above the feed-in limit

19,2 %

Return on storage system with market premium (today 15.7%)

5.0 years

Payback period with market premium (today 6.0)
View Use Case →

20 MWp solar park: redispatch reservation calculated with and without a green electricity storage system

Model calculation for a 20 MWp solar park in the other Direktvermarktung (selling generated power via a direct marketer under the German EEG), under current law and with the redispatch reservation from the draft grid package. Without storage, the internal rate of return falls from 7.0 to 5.4%. With a green electricity storage system, it falls from 9.1 to 8.7%.

5,4 %

Rate of return without storage (today 7.0%)

2.5 GWh

additionally curtailed per year

60 %

of the revenue loss is offset by the storage system

8,7 %

Rate of return with storage (today 9.1%)
View Use Case →

AgNes capacity charge: what happens to the peak shaving calculation from 2029

Same site, same storage system, new grid fee system: the value contribution from peak shaving falls from €19,602/a to minus €4,258/a. The return falls from 11.8 to around 7 per cent.

11,8%

Return until 2028

7,3%

Return from 2029

-100%

Value contribution from peak shaving

43.5k

Additional costs p.a. from AgNes
View Use Case →

MiSpeL BTM with three stakeholders: The free grid connection as a business case

The site has a 750 kW grid connection and uses 413.7 kW of it. How a BESS investor uses the free 336 kW in line with MiSpeL, and what is left for the site and the direct marketer.

12,8%

Investor IRR

-44%

Site operating costs

103k

Total benefit per year

336 kW

Free grid connection
View Use Case →

C&I (commercial and industrial): one storage system, all revenues. The same storage system with and without MiSpeL

A commercial site with 750 kWp of PV is assessing a 2 MWh storage system. The same storage system, calculated twice: with full grid fees and levies on the trading electricity, and MiSpeL-compliant. The net present value (NPV) rises from €287,000 to €762,000.

132k

Savings/year (previously 80k)

762k

NPV (previously 287k)

3.8 yrs

Payback period (previously 6.3)

2,7×

NPV through MiSpeL
View Use Case →

From PPA to energy contracting: how the contract model decides the battery business case

Same site, same PV, but depending on the contract model, the business case ends up almost 10× larger. And the best part: the investor earns, the consumer saves, with no CAPEX of their own.

22,2%

Return

4.8 yrs

Payback period

7.59M

Net present value

-33%

Ongoing costs
View Use Case →