AgNes restructures electricity grid fees from 2029. According to the draft, a site then pays for a capacity ordered in advance instead of its highest load peak of the year, and generators and storage systems pay their own grid fees for the first time.
The Bundesnetzagentur (BNetzA, Germany's Federal Network Agency) published the full draft determination on 6 August 2026. The current system applies until the end of 2028. The consultation ran until 18 September 2026, and the determination is due in 2026.
This rule has not been adopted yet. The figures on this page are based on the stated status and may change significantly before adoption.
The same site, once without and once with the rule.
From 2029, what counts is no longer the single load peak of the year but the capacity a site orders in advance. Exceeding it costs a higher energy charge. Classic peak shaving therefore loses its value in the grid fees, completely so in our example calculation.
Recommendation: only factor in peak shaving until 2028, optimise the ordered capacity as well, and plan self-consumption and arbitrage as your main revenues. The determination is still pending, so details may change.
Every version stays available to read, with its date and what has changed.
All information is provided without warranty. The figures are model calculations for reference cases with fixed assumptions. They are not legal advice and not a forecast for your project. Legal notice