04.12.2026

lcmd onsiteOur next webinar

Grid connection in 2031, charging park in 2027: how you bridge the gap with a storage system and still make the numbers work
Konsultation
Draft of 6 August 2026, determination planned by the end of 2026
Primary source:
BNetzA, draft determination AgNes, GBK-25-01-1#3
→

AgNes, new grid fees system from 2029

What the rule says

AgNes restructures electricity grid fees from 2029. According to the draft, a site then pays for a capacity ordered in advance instead of its highest load peak of the year, and generators and storage systems pay their own grid fees for the first time.

The Bundesnetzagentur (BNetzA, Germany's Federal Network Agency) published the full draft determination on 6 August 2026. The current system applies until the end of 2028. The consultation ran until 18 September 2026, and the determination is due in 2026.

This rule has not been adopted yet. The figures on this page are based on the stated status and may change significantly before adoption.

Status of this page
Responsible
Leander
Assumptions
November 4, 2026
Design
Draft determination 08/2026
Price book
Standard 07/2026
Next step
BNetzA determination, planned by the end of 2026

What the rule changes in the reference case

The same site, once without and once with the rule.

A
Consumers under 10 GWh
BTM
100,000 kWh to 10 GWh/a · interval metering · medium voltage
Preliminary calculation
Peak shaving loses its value under grid fees
In the reference case with 500 MWh, 99 kWp PV and flat electricity procurement, the storage system saves €2,662 in the first year under today's grid fees, €2,453 of it through the load peak. With the capacity charge from €2029,522 a year remains, because the contracted capacity is 46 kW with and without the storage system.
Open financing report →
B
Consumers over 10 GWh
BTM
from 10 GWh/a · interval metering · medium to high voltage
Preliminary calculation
Storage system case stays stable as long as atypische Netznutzung continues
In the reference case with 15 GWh, 5 MWp PV, baseload procurement and spot, the storage system saves €337,025 in the first year under current grid fees, €353,027 under AgNes (BNetzA reform of German grid fees towards capacity-based pricing) in 2029 and €312,878 in 2031. The calculation continues atypische Netznutzung for the storage system site. The successor rule will come in a separate procedure on industrial grid fees and is still open.
Open financing report →
C
Generators and storage systems
FTM
own grid connection from approx. 1 MW · medium to high voltage
Preliminary calculation
New grid fee on feed-in capacity
In the reference case with 20 MWp of ground-mounted PV, the green electricity storage system generates €1.22 million in additional revenue in the first year under current rules. From 2029, the park pays a grid fee on its feed-in capacity, calculated at €5.5 per kW per year. The storage system raises this capacity from 13,187 to 20,000 kW, and its additional revenue falls by 2.6% to €1.19 million.
Open financing report →

Result and recommendation

From 2029, what counts is no longer the single load peak of the year but the capacity a site orders in advance. Exceeding it costs a higher energy charge. Classic peak shaving therefore loses its value in the grid fees, completely so in our example calculation.

Recommendation: only factor in peak shaving until 2028, optimise the ordered capacity as well, and plan self-consumption and arbitrage as your main revenues. The determination is still pending, so details may change.

Change history

Every version stays available to read, with its date and what has changed.

A · Consumers under 10 GWh
B · Consumers over 10 GWh
C · Generators and storage systems
October 1, 2026
Determination 10/2026
BNetzA adopts the determination. Transition period until the end of September 2027. Until then, only with the consent of the grid operator and the metering point operator.
Dr.-Ing. Leander König-Kotzur
MiSpeL
September 24, 2026
Government draft 07/2026
First reading in the Bundestag, referred to the Committee on Economic Affairs and Energy. The hearing was held on 5 October 2026.
Dr.-Ing. Leander König-Kotzur
EEG 2027
August 6, 2026
Draft determination 08/2026
The Bundesnetzagentur publishes the full draft determination and starts the consultation.
Dr.-Ing. Leander König-Kotzur
AgNes
May 27, 2026
Interim status 05/2026
BNetzA presents its interim status. From 2029, generators are to pay a grid fee of around €4 to €7 per kW and year.
Dr.-Ing. Leander König-Kotzur
AgNes
September 18, 2025
Consultation draft 09/2025
BNetzA puts the key points and the draft determination out for consultation.
Dr.-Ing. Leander König-Kotzur
MiSpeL
No items found.

Run the numbers
on your project.

All information is provided without warranty. The figures are model calculations for reference cases with fixed assumptions. They are not legal advice and not a forecast for your project. Legal notice