Grid connection in 2031, charging park in 2027: how you bridge the gap with a storage system and still make the numbers work
Regulation
/
MiSpeL
In Kraft
decided on 1 October 2026, transition until 09/2027
Primary source:
BNetzA, determination MiSpeL, ref. 618-25-02
→

MiSpeL, mixed use of storage systems

What the rule says

MiSpeL governs how a storage system may use green electricity and grid electricity together. Under the determination of 1 October 2026, a storage system can combine self-consumption and electricity trading, while funding and levy privileges are retained proportionally.

The Bundesnetzagentur (BNetzA, Germany's Federal Network Agency) adopted the determination on 1 October 2026. The separation option allocates electricity volumes in 15-minute intervals using fixed formulas. The flat-rate option simplifies this for PV systems up to 30 kWp. Until the end of September 2027, its use requires the consent of the grid operator and the metering point operator.

This rule has not been adopted yet. The figures on this page are based on the stated status and may change significantly before adoption.

Status of this page
Responsible
Leander
Assumptions
October 29, 2026
Design
Determination 10/2026
Price book
Standard 07/2026
Next step
End of transition period 09/2027

What the rule changes in the reference case

The same site, once without and once with the rule.

A
Consumers under 10 GWh
BTM
100,000 kWh to 10 GWh/a · interval metering · medium voltage
Preliminary calculation
Arbitrage in addition to self-consumption and peak shaving
In the reference case with 5 GWh, baseload procurement and spot, the storage system with MiSpeL (German BNetzA rules for storage that charges both grid power and on-site renewable power) reaches a return of 42.2 % and a payback period of 2.3 years. The comparison without MiSpeL follows.
Open financing report →
B
Consumers over 10 GWh
BTM
from 10 GWh/a · interval metering · medium to high voltage
Preliminary calculation
Arbitrage in addition to self-consumption and peak shaving
In the reference case with 15 GWh, baseload procurement and spot, the storage system with MiSpeL (German BNetzA rules for storage that charges both grid power and on-site renewable power) delivers a 42.0% return and a payback period of 2.3 years. The comparison without MiSpeL follows.
Open financing report →
C
Generators and storage systems
FTM
own grid connection from approx. 1 MW · medium to high voltage
Preliminary calculation
Charge grid electricity, keep the market premium proportionally
Until now, a storage system at a subsidised solar park lost its support as soon as it charged grid electricity. With the separation option, the market premium remains for the green electricity share. The reference calculation for a 20 MWp site follows.
Open financing report →

Result and recommendation

A storage system behind the meter can now store grid electricity and trade it on the market. Funding and levy privileges are retained proportionally. How much this brings depends on the site, above all on electricity procurement, PV marketing and grid connection.

Recommendation: include arbitrage in every storage system sizing and compare it with the scenario without it. For projects before the end of September 2027, talk to the grid operator and the metering point operator early.

Change history

Every version stays available to read, with its date and what has changed.

A · Consumers under 10 GWh
B · Consumers over 10 GWh
C · Generators and storage systems
October 1, 2026
Determination 10/2026
BNetzA adopts the determination. Transition period until the end of September 2027. Until then, only with the consent of the grid operator and the metering point operator.
Dr.-Ing. Leander König-Kotzur
MiSpeL
September 24, 2026
Government draft 07/2026
First reading in the Bundestag, referred to the Committee on Economic Affairs and Energy. The hearing was held on 5 October 2026.
Dr.-Ing. Leander König-Kotzur
EEG 2027
August 6, 2026
Draft determination 08/2026
The Bundesnetzagentur publishes the full draft determination and starts the consultation.
Dr.-Ing. Leander König-Kotzur
AgNes
May 27, 2026
Interim status 05/2026
BNetzA presents its interim status. From 2029, generators are to pay a grid fee of around €4 to €7 per kW and year.
Dr.-Ing. Leander König-Kotzur
AgNes
September 18, 2025
Consultation draft 09/2025
BNetzA puts the key points and the draft determination out for consultation.
Dr.-Ing. Leander König-Kotzur
MiSpeL
No items found.

Run the numbers
on your project.

All information is provided without warranty. The figures are model calculations for reference cases with fixed assumptions. They are not legal advice and not a forecast for your project. Legal notice