04.12.2026

lcmd onsiteOur next webinar

Grid connection in 2031, charging park in 2027: how you bridge the gap with a storage system and still make the numbers work
Use Case

BESS meets thermal storage: the sweet spot lies in the combination

Large industrial site with a near 1:1 ratio of electricity to heat demand: why BESS or thermal storage alone fall short of their potential, and why the combination with PV ends at a 72.2% return and a 1.4-year payback period.

Use Case key data

72,2%

Return

1.4 yrs

Payback period

71.7M

Net present value

-26%

Operating costs

A large industrial site with an electricity demand of 138,621 MWh/a and a heat demand of 132,534 MWh/a, a near 1:1 ratio. Operating costs: €27.4 million/a. Price book: MISPEL (German BNetzA rules for storage that charges both grid power and on-site renewable power) 2026 (beta), WACC 6%, 20 years. This exact ratio is what makes the combined effect so strong: with a lower share of heat, the effect is correspondingly smaller.

BESS only or thermal storage only?

BESS only (4,890 kWh): €1.22 million investment, €749k net present value, 12.4% return, 7.4-year payback period. The storage system reduces load peaks, but the site's large heat share remains economically unused.

Thermal storage only (13,302 kWh): €399k investment, €2.44 million net present value, 62% return, 1.6-year payback period. With a third of the investment, you get three times the net present value, because the thermal storage makes the heat pump flexible and optimises electricity purchasing costs in low-cost hours.

The sweet spot: both systems combined

€9.77 million investment: 72.2% return, 1.4-year payback period, €71.7 million net present value.

BESS (432.4 kWh) and thermal storage (105,317 kWh) act on the same lever (the electricity price), but on two levels at once: the battery optimises procurement and peak shaving in the power grid. The thermal storage decouples the heat pump from heat demand and maximises its running time in low-cost hours. A 10 MWp PV system also complements the setup, with savings over 20 years of €140.9 million. Together they multiply, but only because heat and electricity demand are on a par here.

And then? atypische Netznutzung (atypical grid usage under § 19(2) StromNEV, reduced grid fees for shifting load out of HLZF) keeps scaling

+atypische Netznutzung (87,343 kWh BESS): €21.8 million investment, 31.9% return, €58.3 million net present value. Sensible for very large portfolios, but the return falls because capital rises disproportionately.

Sign up once and stay informed

What our customers calculate with it.

Commercial roof with 99 kWp: EEG 2027 calculated with feed-in limit and market premium

Model calculation for a commercial business with 500 MWh consumption and 99 kWp PV, under current law and under the draft EEG 2027. Because the business consumes 87% of its PV power itself, the feed-in limit barely changes the result. With a market premium, the benefit of the storage system rises by 10%.

87 %

Self-consumption rate of the PV system

0,3 %

of generation lies above the feed-in limit

19,2 %

Return on storage system with market premium (today 15.7%)

5.0 years

Payback period with market premium (today 6.0)
View Use Case →

20 MWp solar park: redispatch reservation calculated with and without a green electricity storage system

Model calculation for a 20 MWp solar park in the other Direktvermarktung (selling generated power via a direct marketer under the German EEG), under current law and with the redispatch reservation from the draft grid package. Without storage, the internal rate of return falls from 7.0 to 5.4%. With a green electricity storage system, it falls from 9.1 to 8.7%.

5,4 %

Rate of return without storage (today 7.0%)

2.5 GWh

additionally curtailed per year

60 %

of the revenue loss is offset by the storage system

8,7 %

Rate of return with storage (today 9.1%)
View Use Case →

AgNes capacity charge: what happens to the peak shaving calculation from 2029

Same site, same storage system, new grid fee system: the value contribution from peak shaving falls from €19,602/a to minus €4,258/a. The return falls from 11.8 to around 7 per cent.

11,8%

Return until 2028

7,3%

Return from 2029

-100%

Value contribution from peak shaving

43.5k

Additional costs p.a. from AgNes
View Use Case →

MiSpeL BTM with three stakeholders: The free grid connection as a business case

The site has a 750 kW grid connection and uses 413.7 kW of it. How a BESS investor uses the free 336 kW in line with MiSpeL, and what is left for the site and the direct marketer.

12,8%

Investor IRR

-44%

Site operating costs

103k

Total benefit per year

336 kW

Free grid connection
View Use Case →

C&I (commercial and industrial): one storage system, all revenues. The same storage system with and without MiSpeL

A commercial site with 750 kWp of PV is assessing a 2 MWh storage system. The same storage system, calculated twice: with full grid fees and levies on the trading electricity, and MiSpeL-compliant. The net present value (NPV) rises from €287,000 to €762,000.

132k

Savings/year (previously 80k)

762k

NPV (previously 287k)

3.8 yrs

Payback period (previously 6.3)

2,7×

NPV through MiSpeL
View Use Case →

From PPA to energy contracting: how the contract model decides the battery business case

Same site, same PV, but depending on the contract model, the business case ends up almost 10× larger. And the best part: the investor earns, the consumer saves, with no CAPEX of their own.

22,2%

Return

4.8 yrs

Payback period

7.59M

Net present value

-33%

Ongoing costs
View Use Case →