Grid connection in 2031, charging park in 2027: how you bridge the gap with a storage system and still make the numbers work
Use Case

Calculating battery storage on a leasing basis with an existing on-site PPA

An EPC operates a PV system under an on-site PPA and wants to calculate an economically optimal Multi-Use storage system on a leasing basis for the customer.

Use Case key data

543k

Multi-Use/a

12,8%

IRR investor

+269k

Net end customer/a

7 years

Payback period

An industrial customer has been buying electricity for several years through a local PPA with a 2 MWp PV system at an energy charge of 14 ct/kWh. Despite low-cost solar power, annual energy costs were still €1.1 million. Goal: identify an economically optimal battery storage in an energy contracting model that creates added value for both tenant and investor.

Method

In minimum energy, a stakeholder model was set up between the tenant and the investor .
A fee of €35/kWh/a was agreed for the energy contracting. The optimisation looked for the best storage size in economic terms across all Multi-Use potentials (peak shaving, PV shift, arbitrage).

Result

The optimal design is a 6.4 MWh storage system with a total Multi-Use benefit of €543,000 per year.

Tenant perspective

  • Energy contracting     fee: €262,000/year
  • Net savings     through Multi-Use: +€269,000/year

Investor perspective

  • Payback period:     7 years
  • Return     (IRR): 12.8%

Conclusion

A clear win-win case:
Despite the energy contracting fee, the tenant significantly cuts energy costs, while the investor achieves an attractive and predictable return. The combination of a local PPA, a storage retrofit and Multi-Use optimisation shows clearly how C&I sites can be decarbonised economically today.

Sign up once and stay informed

Here is how you can calculate it:

What our customers calculate with it.

Commercial roof with 99 kWp: EEG 2027 calculated with feed-in limit and market premium

Model calculation for a commercial business with 500 MWh consumption and 99 kWp PV, under current law and under the draft EEG 2027. Because the business consumes 87% of its PV power itself, the feed-in limit barely changes the result. With a market premium, the benefit of the storage system rises by 10%.

87 %

Self-consumption rate of the PV system

0,3 %

of generation lies above the feed-in limit

19,2 %

Return on storage system with market premium (today 15.7%)

5.0 years

Payback period with market premium (today 6.0)
View Use Case →

20 MWp solar park: redispatch reservation calculated with and without a green electricity storage system

Model calculation for a 20 MWp solar park in the other Direktvermarktung (selling generated power via a direct marketer under the German EEG), under current law and with the redispatch reservation from the draft grid package. Without storage, the internal rate of return falls from 7.0 to 5.4%. With a green electricity storage system, it falls from 9.1 to 8.7%.

5,4 %

Rate of return without storage (today 7.0%)

2.5 GWh

additionally curtailed per year

60 %

of the revenue loss is offset by the storage system

8,7 %

Rate of return with storage (today 9.1%)
View Use Case →

AgNes capacity charge: what happens to the peak shaving calculation from 2029

Same site, same storage system, new grid fee system: the value contribution from peak shaving falls from €19,602/a to minus €4,258/a. The return falls from 11.8 to around 7 per cent.

11,8%

Return until 2028

7,3%

Return from 2029

-100%

Value contribution from peak shaving

43.5k

Additional costs p.a. from AgNes
View Use Case →

MiSpeL BTM with three stakeholders: The free grid connection as a business case

The site has a 750 kW grid connection and uses 413.7 kW of it. How a BESS investor uses the free 336 kW in line with MiSpeL, and what is left for the site and the direct marketer.

12,8%

Investor IRR

-44%

Site operating costs

103k

Total benefit per year

336 kW

Free grid connection
View Use Case →

C&I (commercial and industrial): one storage system, all revenues. The same storage system with and without MiSpeL

A commercial site with 750 kWp of PV is assessing a 2 MWh storage system. The same storage system, calculated twice: with full grid fees and levies on the trading electricity, and MiSpeL-compliant. The net present value (NPV) rises from €287,000 to €762,000.

132k

Savings/year (previously 80k)

762k

NPV (previously 287k)

3.8 yrs

Payback period (previously 6.3)

2,7×

NPV through MiSpeL
View Use Case →

From PPA to energy contracting: how the contract model decides the battery business case

Same site, same PV, but depending on the contract model, the business case ends up almost 10× larger. And the best part: the investor earns, the consumer saves, with no CAPEX of their own.

22,2%

Return

4.8 yrs

Payback period

7.59M

Net present value

-33%

Ongoing costs
View Use Case →