Flexible connection agreement (FCA): what a restricted grid connection really costs

Table of contents

More about the author

Dr.-Ing. Leander König-Kotzur

Managing Director Product

Go to author page
Go to Google Scholar profile

More about the co-author

Dr.-Ing. Felix Kullmann

Managing Director Customer Success

Go to author page
Go to Google Scholar profile

Share this post

Key takeaways from this article:

  • It is not the FCA that decides, but the individual clause. The same restriction costs 0.6% or 16%, depending on whether it follows the grid state or is set as a blanket limit.
  • At a real grid connection in northern Germany, the dynamic, wind-coupled feed-in restriction cost 0.6% of 2025 annual revenue. It applies in strong-wind hours, which are the hours with the lowest prices.
  • Losing the ability to provide balancing services cost 33%, more than fifty times as much. FCR and aFRR made up 50.4% of baseline revenue.
  • Every ramp rate in the range under discussion today, 1 to 20% per minute, rules out FCR. What matters is not the level of the ramp, but whether it also applies to system services.
  • Without balancing services, battery throughput rises by 43% while revenue falls by a third. An FCA that curtails balancing services therefore also costs cycles.

Two clauses in the same contract, a factor of more than fifty in revenue. The dynamic feed-in restriction cost 0.6% of 2025 annual revenue at a real grid connection in northern Germany. Losing balancing services cost 33%. Judging FCAs as a whole means judging the wrong thing.

In June 2026, connection requests for battery storage at E.ON's distribution system operators exceeded 500 GW, with around 25 GW confirmed. Nationwide, only about 2.6 GW of grid-scale storage was in operation at the end of 2025, against an annual peak load of 75 to 80 GW. The requests therefore exceed the maximum quarter-hourly demand of the whole country many times over, and grid operators have found an instrument for this: the flexible grid connection. E.ON plans to roll out a group-wide FCA standard for storage systems by the end of 2026. In April, Schleswig-Holstein Netz signed its first contract with a biogas plant. Netze BW, Bayernwerk, MITNETZ and others are following.

As a planner, EPC or project developer, this means the question is less and less whether you get a grid connection. It is which conditions come with it. And you have to base a decision on that for which hardly any reliable figures exist so far. This article sets out what a flexible connection agreement is, which clauses cost how much, and how you compare an FCA now with a full connection later.

What a flexible connection agreement is

A flexible connection agreement (FCA) is a contract between the grid operator and the connecting party that temporarily limits feed-in or consumption capacity at the grid connection point. In return, the connection comes earlier, often with no grid reinforcement or with significantly less. You swap the always guaranteed capacity of a conventional connection for a conditional capacity that is curtailed in defined situations.

The physical reason this works: grids are designed for rare extreme situations. A grid connection point with PV is utilised at 13% on annual average, and with modern wind power at 33% (BEE and Fraunhofer IEE, 2024). Between the peaks there is capacity that nobody uses. The FCA opens up this reserve by scaling the plant back in exactly the critical hours.

Neon, commissioned by ECO STOR, calculated what a market-driven grid-scale battery actually does to the grid at the storage system in Bollingstedt, the 103.5 MW project in Schleswig-Holstein that went into operation in April 2025. Over 2024, the plant relieved the grid in 24% of quarter-hours and loaded it in 20%. The rest of the time it stood idle or the grid was free of congestion. At the comparison site Plattling in southern Germany, 21% relief is set against 22% load. On balance, grid operators save €3 to 6 in redispatch costs per kW and year. Neon's conclusion is therefore not that storage systems are harmless, but that they are neither generally supportive of the grid nor generally a burden on it. In this sense, there is no systematically grid-supportive site. That is exactly the argument against a blanket FCA: it applies in hours when the plant helps the grid just as much as in hours when it loads it.

Against this stands a finding that should not get lost. Redispatch frequency and the design case are two different questions. BET Consulting and IAEW show that simply superimposing a real distribution grid load profile with the profile of an unrestricted, market-optimised storage system already raises the annual peak load significantly, in extreme cases by almost the full connection capacity. A storage system can therefore be grid-neutral over the year and still drive the need for grid expansion. Both belong in the discussion.

Legally, two provisions stand behind this in Germany. Both were introduced with the Solarspitzengesetz (German solar peak law of February 2025) and have been in force since 25 February 2025. § 8a EEG covers the flexible connection agreement for generation plants, that is, on the feed-in side for PV, wind and biogas. § 17(2b) EnWG covers it for battery storage, and it does so bidirectionally for grid feed-in and grid import. The law prescribes minimum content: the level of the capacity limit, periods, duration, technical requirements and liability for exceeding the limit.

You need to know three things before you negotiate. First, the FCA is voluntary for both sides. You do not have to sign, and the grid operator does not have to offer you one. The Bundesnetzagentur (BNetzA, Germany's Federal Network Agency) confirmed this on 30 March 2026 in proceeding BK6-25-325: A grid operator that refuses the connection of a grid-scale storage system for grid security reasons must justify this case by case, but is not obliged to offer an FCA. Second, an FCA is not redispatch. If you stay within the agreed limit, you are not compensated. There are no compensation claims under § 13 EnWG for the contractually limited capacity. Third, there is still no determination by the Bundesnetzagentur on how FCAs should be designed. As long as that is missing, the grid operators define the rules, and every FCA is a individual case.

That makes the flexible grid connection a negotiation, not an allocation. And anyone who goes into a negotiation without numbers takes whatever is on the table.

Static or dynamic: The clause decides, not the instrument

FCAs are often judged as a whole, as if there were only one type. In fact, the contracts differ so much in their mechanics that the term alone says nothing about economic viability.

Dynamic FCAs tie the permitted capacity to the actual state of the grid. Schleswig-Holstein Netz uses this variant in areas with a lot of wind: The more wind and PV feed into the grid area, the less the plant is allowed to feed in. Among several grid operators, practice is now converging on a rule-based capacity band. The permitted capacity is tied to the output of neighbouring wind and PV reference plants and falls linearly to zero above a kink point of 50, 40 or 30% of the reference output. The grid operator sets which kink point applies specifically for each grid connection point.

Static FCAs, by contrast, specify fixed time windows or a year-ahead envelope curve. In grids dominated by PV, the start and end time of permitted feed-in is fixed for each month. Bayernwerk Netz works with envelope curves that limit feed-in and import capacity depending on time of day and season, based on the typical local grid load profile: a feed-in restriction around the midday peak, an import restriction in the morning and evening. Static is predictable and requires little process effort for the grid operator. The price: The curtailment also applies in hours when the grid is not at its limit at all.

A case study by our webinar partner inframind, based on a real 20 kV load profile from 2023 to 2025, shows how big the difference between the two approaches is in practice. The site: an industrial plant with 25 MW of secured import capacity, a 40 MVA transformer and 15.8 MWp of rooftop PV, plus a 10 MW storage system. A dynamic envelope curve, derived from measured grid behaviour, restricted the storage system in 3.1% of quarter-hours. The flat static approach applied in 37.4% of quarter-hours, which is roughly twelve times as often. And the medium static scenario was also the only one that actually breached the connection limit. Flat limits are therefore not conservative. They are too strict and too risky at the same time.

On top of this come clauses that appear in both models and have their own effect: ramp limits between 1 and 20% of rated power per minute, caps on participation in balancing services markets, night charging windows, lead times and, if present at all, caps on full-load hours for the restriction. The ramp looks like a technical detail and is in fact the clause with the greatest leverage. The reason follows below.

What restrictions cost in revenue: our calculation

Together with inframind, we ran the numbers for a real grid area. Site: Reußenköge in North Frisia, in the Schleswig-Holstein Netz grid area, with a lot of wind. inframind derived the dynamic capacity band from grid simulations and the grid operator's restrictions, and we fed it into the dispatch optimisation as a constraint at 15-minute resolution. Plant: a standalone storage system with 10 MW connection capacity and 20 MWh, so two hours, marketed via Day-Ahead, Intraday auction, continuous Intraday, FCR and aFRR.

Revenue 2025 per MW of connection capacity

  • Unrestricted connection (baseline): €217,500.
  • Dynamic feed-in restriction, wind-coupled: €216,200. Minus 0.6% compared with the baseline.
  • Dynamic feed-in restriction and loss of balancing services: €144,900. Minus 33.4% compared with the baseline.

Source: minimum energy and inframind, Grid Connection Report Vol. 2, September 2026.

How we calculated. 10 MW / 20 MWh, price year 2025, cross-market across Day-Ahead, Intraday auction, continuous Intraday, FCR and aFRR, at 15-minute resolution over 35,040 time steps. Optimisation with foresight of the actual 2025 market prices, with a friction markup in continuous Intraday. Cycle cap of 730 per year. Not included: degradation and augmentation costs, route-to-market fees, ramping costs. The grid fee exemption under § 118(6) EnWG is assumed for the whole term. The AgNes (BNetzA reform of German grid fees towards capacity-based pricing) consultation belongs above this as a scenario, not as a base assumption. The values are revenue potentials of a generic storage system at a specific grid connection point, not a statement about your project.

The most important finding is in the second line. The dynamic feed-in restriction, which is exactly what the industry argues about, cost 0.6%. The reason is economically trivial and rarely spoken: In a grid area with a lot of wind, the restriction binds in high-wind hours. These are the hours with the lowest prices, so exactly the hours in which the storage system does not want to feed in anyway. The curtailment is negatively correlated with the value of feed-in. It takes almost nothing away from the storage system that it would have wanted to earn.

This matches the short study by BET Consulting and the IAEW of RWTH Aachen, which reports a revenue loss of around 1% for highly dynamic limits with good forecast quality, while year-round static restrictions cost up to 26% there. This spread is exactly the point: the instrument does not decide, but whether the curtailment follows the actual state of the grid or is set as a flat limit.

The economic damage arises elsewhere. The loss of the ability to provide balancing services cost 33%, which is more than fifty times as much as the energy curtailment. In our case, FCR and aFRR accounted for 50.4% of the baseline revenue. If this pillar drops away, the storage system shifts to the wholesale markets and wins back part of it there, but only part: Spot revenues rose by 34%, while total revenue fell by a third.

One caveat belongs here: the size of this 33% is a finding for price year 2025. If you expect balancing services prices to fall because storage build-out saturates the markets, you arrive at a smaller figure. Modo Energy considers a 50% balancing services restriction almost ineffective looking forward, precisely because these markets are likely to saturate in the coming years. The ranking of the clauses stays, but the absolute size depends on your price assumption. Treat it as a sensitivity, not as a constant.

Losing balancing services costs revenue and cycles

One effect is missing from the discussion: the case without balancing services runs more throughput, not less. In our calculation, battery throughput rose from 6.92 to 9.92 GWh, an increase of 43%, while revenue fell by a third. The reason is the same as for the revenue loss. Without balancing services, the storage system has to earn its money through energy trading, and energy trading means cycles. The dynamic grid feed-in restriction on its own, by contrast, barely changed throughput. EERA observes the same effect with capacity limits per balancing services market, where full cycles rise from 674 to 724.

For the negotiation, this means: an FCA that curtails balancing services costs not only revenue but also battery life. If you calculate the net present value (NPV), you have to offset the higher augmentation requirement. It is not included in our figures above, so the deltas should be read as conservative.

Cross-validation

The best publicly documented clause-by-clause sensitivity comes from EERA Consulting (Battery Beats, 20 February 2026). It was calculated retrospectively for a 1 MW/2 MWh storage system using the real market prices of 2025. It provides the reference points that we have not calculated ourselves, each with balancing services marketing retained: a ramp of 10% per minute minus 0.4%, 5% per minute minus 1.9%, 1% per minute minus 9%. A capacity limit of 30% per balancing services market minus 14%. A PV-dominated envelope curve based on the Bayernwerk approximation minus 16%. All three combined minus 32%. Here too, intervening in balancing services is more expensive than capping energy, and here too the effects do not add up linearly.

EERA's baseline is around €263,000 per MW, ours is €217,500. The gap of about 17% is explained by the foresight horizon, the friction premium in continuous Intraday and a different allocation of revenues between the sequential spot markets. In market structure, the two calculations are close to each other: aFRR around €126,000 per MW for us against €132,000 for EERA, FCR €17,000 against €20,000, spot in total €108,000 against €111,000.

A third data point puts the series in context. Neon calculates a market added value of €199 per kW for Bollingstedt for 2024, based on ECO STOR's real-world marketing simulation with limited foresight across Day-Ahead, Intraday, FCR and aFRR. That puts €199,000 per MW (2024, limited foresight), our €217,500 (2025) and EERA's €263,000 (2025, perfect foresight) in a methodologically plausible order: the more foresight the model assumes, the higher the baseline.

A note on comparability, because otherwise it leads to wrong conclusions. In the same study, Neon assesses a dynamic guardrail, meaning a ban on operation that burdens the grid, and arrives at a loss of around 20% in market added value. This does not contradict our 0.6%, it is a different instrument. Neon's guardrail works bidirectionally, so depending on the redispatch sign it also prohibits charging, and it binds about half the time in the north-west. The restriction calculated here, by contrast, limits only grid feed-in and only above a wind threshold. From this, Neon concludes that grid-supportive behaviour is better incentivised through a redispatch price signal than through operating restrictions, a position that fits well with our ranking of the clauses.

In its own white paper, inframind arrives at a range for a 100 MW/200 MWh storage system, from 8% with a PV-coupled grid feed-in restriction to 29% with a tight ramp plus a balancing services cap. Three independent calculations, the same ranking of the clauses.

The valuation gap

What these figures show together is less a result than a problem. The same clause can cost 0.6% or 16%, depending on whether it follows the grid state or is set as a flat rule. The same envelope curve binds in 3.1% or in 37.4% of quarter-hours, depending on whether it was derived from measured grid behaviour or estimated. If you value an FCA with a flat revenue discount, you carry this spread as a risk without knowing it. This is the valuation gap that arises when nobody includes the grid situation at the connection point in the calculation, and it cuts both ways. It leads to viable projects being written off and to unviable clauses being signed.

This becomes especially clear at Bollingstedt. The storage system that Neon modelled, whose grid impact over 2024 was almost neutral, is the same one on which E.ON tested its nationwide FCA standard. A pilot site with a roughly balanced grid impact does not yield flat parameters for all grid areas. Which clause is justified at your connection point is decided by the grid situation there, not by a standard derived from a single pilot.

The ramp is not a revenue brake, it is a market access clause

The most discussed parameter in FCA negotiations is the power gradient, stated as a percentage of rated power per minute. The discussion about it is almost always conducted wrongly, because it treats the gradient as a gradual revenue brake.

As a revenue brake, it is in fact harmless. The EERA values above show this: with balancing services marketing retained, a ramp of 5% per minute costs less than 2% of revenue, and at 10% per minute the effect is barely measurable. Only at 1% per minute does the slower arbitrage turn into around 9%.

The real effect lies elsewhere, namely in the full activation times of the balancing services products. FCR must be delivered in full within a maximum of 30 seconds at a frequency deviation of ±200 millihertz. aFRR is called up via a setpoint signal from the transmission system operator and must be fully adjusted within 5 minutes. This Full Activation Time is set in binding European rules. Expressed as a gradient, that corresponds to 200% per minute for FCR and 20% per minute for aFRR.

Two things follow from this. First: the whole range of 1 to 20% per minute under discussion today rules out FCR. At 2% per minute, the storage system reaches 1% of its rated power in 30 seconds. FCR is not restricted, it is gone. Second: a ramp rate below 20% per minute means the system cannot meet the full activation time for its entire capacity. How much aFRR volume can still be prequalified is a question to settle between the transmission system operator, the grid operator and the marketer, and it is exactly the question you need to clarify before you sign. We quantify it in the Grid Connection Report Vol. 2.

So the decisive question in the contract is not the level of the ramp rate, but whether it applies to the provision of ancillary services at all. For grid-driven measures such as Redispatch, FCR and aFRR, the transmission system operators grant separate, faster ramp rates, because these services help the grid directly. The distribution system operators have no harmonised rule on this, often set stricter ramps and have less incentive to make exceptions for frequency containment services. A battery that responds to national frequency deviations can still cause local voltage problems. The carve-out does exist in market practice: marketers report FCAs in which the ramp rate applies expressly to spot market trading only.

In our case, the value of that one sentence in the contract can be quantified. It is the third line of the breakdown above: around €1.1 million per year for the 10 MW storage system, 50.4% of the revenue.

What is in force, what is in the legislative process, what remains announced

For the calculation, you need to separate three levels, because they enter the calculation in different ways.

Law in force, as at September 2026: § 8a EEG and § 17(2b) EnWG since February 2025. In its decision of 15 July 2025 (EnVR 1/24), the BGH confirmed that a Baukostenzuschuss (construction cost contribution for a grid connection in Germany) for battery storage is permissible under the capacity-price model. Anyone who accepts limited capacity still currently pays the full Baukostenzuschuss on the connection capacity. The Bundesnetzagentur (BNetzA, Germany's Federal Network Agency) decision of 30 March 2026 clarifies that there is no obligation to use an FCA. This is the basis you calculate with today.

In the legislative process: The grid package has been available as Bundestagsdrucksache 21/7734 since 26 August 2026, deliberations begin in September and entry into force is planned for 1 January 2027. Among other things, the discussion covers limiting the voluntary nature of the arrangement on the grid operator side, that is, introducing an obligation to offer or conclude flexible grid connections. How much of that ends up in the law is open. If you are negotiating today, you should know where the process stands, but not calculate on it. In parallel, the Bundesnetzagentur's AgNes (BNetzA reform of German grid fees towards capacity-based pricing) consultation is running, which among other things puts the grid fee exemption for storage systems under § 118(6) EnWG up for review. Both belong in the calculation as scenarios, not as a baseline assumption.

Announced: The E.ON standard is due to be rolled out by the end of 2026, and E.ON has not published concrete parameters such as ramp, balancing services limit or full-load hours. BDEW and Fachagentur Wind und Solar are working on model contracts. A BNetzA determination of its own on FCAs is not expected before 2027. The BVES calls for a cap of around 800 full-load hours of restriction per year, while EWE and EnBW have proposed 200 hours for renewable plants. None of this belongs in the calculation. All of it belongs in your negotiating position.

FCA now or full connection later: the net present value (NPV) question

The real decision is not whether an FCA is good or bad. It is this: is a restricted connection today worth more than a full connection in three, five or seven years? Lead times for transformers and substations are in some cases over 50 months. In some grid areas, according to inframind, storage projects in the queue have no prospect of being realised before 2030.

This question cannot be answered with a flat discount. An envelope curve that constrains the storage system in 3% of quarter-hours has a different effect from one that affects 37%. A ramp that rules out balancing services does not cost a few per cent of revenue but an entire revenue stream, because prequalification is a threshold and not a gradient. And whether the restriction still binds in year five depends on capacity additions in the grid area and on grid expansion.

That is why we calculate it differently. The grid operator's capacity band goes into the dispatch optimisation as a constraint, at quarter-hour resolution over a full year, 35,040 time steps. Each clause is calculated individually: static cap, time window, ramp, balancing services exclusion, each with its delta in NPV. Then the FCA case is set against the full connection with waiting time as a parameter. You enter your own waiting time and see from which year waiting costs more than the restriction.

What we learned contradicts the debate on one point and confirms it on another. The loss of profitability from pure energy curtailment is smaller than the discussion suggests, at least when the curtailment follows availability and therefore prices. 0.6% on a capacity band derived from real data is not a side note, it is the result. For interventions in balancing services, this expressly does not hold. That is exactly why we judge clauses, not FCAs.

The second benefit of this calculation is the one hardly anyone thinks of. Optimised operation changes the load profile at the grid connection point. If you go to the distribution system operator with an annual profile instead of an enquiry, you have a different conversation. The grid operator can read when the system loads the grid and when it relieves it. A flat rate becomes a justifiable characteristic curve. A transparently derived grid calculation cannot be rejected out of hand without the grid operator disclosing its own data basis.

Not just grid-scale storage: three situations, the same decision

The FCA debate is conducted around grid-scale storage. But the decision arises in three situations.

You want to feed in and do not get the full capacity. PV park, wind farm, commercial roof. § 8a EEG applies here. You want to connect a storage system, in front of or behind the meter. § 17(2b) EnWG applies here, in both directions. And you need more import capacity for a fleet, heat or production, while grid expansion takes longer than your project. With a storage system at the grid connection point, the flexible grid connection becomes the route that does not wait. You electrify while your competitor waits for the binding quote.

One distinction: a pure consumer without a storage system falls under neither of the two regimes. For controllable consumption devices, § 14a EnWG (German rule on grid-controlled heat pumps and charging points in exchange for reduced grid fees) is the framework, not the FCA. How special grid fee arrangements differ from this is explained in the glossary entry on atypical grid use.

{{use-case}}

Five thresholds for the negotiation

The ramp rate. It costs less revenue than you think, and more market access. On the energy side, a ramp of 5% per minute stays below 2% revenue loss according to EERA. On the balancing services side, aFRR requires full activation within 5 minutes, which is 20% per minute, and FCR within 30 seconds, which is 200% per minute. Every ramp rate in the band of 1 to 20% per minute under discussion today rules out FCR. Don't ask whether the ramp is strict. Ask how much balancing services volume it leaves you.

The ancillary services carve-out. It is the most valuable clause in the whole contract and the one people ask about least: does the ramp rate also apply to the provision of ancillary services, or only to scheduled and spot market trading? The TSOs allow faster ramp rates for grid-driven measures, while distribution system operators have no harmonised rule on this. If the contract contains no carve-out, you calculate the storage system without balancing services. In our case, that would have been around 50% of revenues in 2025.

The full-load hours. An envelope without a cap on curtailment hours is hard to present for financing, because the loss is open-ended. A cap, as is common in the British model via a curtailment index, should be a negotiation target.

The balancing services cap. According to EERA, a flat limit of 30% per market cost more in 2025 than any envelope. If the grid operator sets a cap, ask for the technical grid justification. Balancing service calls are short and rarely critical for the grid, and balancing services currently take priority even in the case of redispatch.

The conversion. Under Art. 6a of the EU Electricity Market Directive, FCAs are meant to be converted into firm connections after grid expansion. If the contract says nothing on this, you calculate the restriction over the full term. If it names a date or a trigger, that changes the net present value (NPV) considerably.

What you can do now

If an FCA quote is on your table or one is foreseeable: ask the grid operator to give you the clauses individually, not as a package. Check the ramp rate and the ancillary services carve-out first, because that is where the largest sums sit. Calculate each clause individually over a full year, with the power band as a boundary condition rather than a deduction. Compare the case with your realistic wait for the full connection. And take the optimised load profile into your next conversation with the distribution system operator.

In Grid Connection Report Vol. 2, we calculate this together with inframind on real grid areas, from a wind-heavy site in northern Germany to a PV-heavy site in southern Germany with a time window around the midday peak. inframind derives the power band from the grid model, and minimum energy calculates what each clause costs in net present value (NPV). If you want to read the basis first: Vol. 1 shows which assets are economically viable on a free grid connection.

{{cta}}

Frequently asked questions about the flexible connection agreement

Do I have to accept an FCA if the grid operator offers one?
No. § 8a EEG and § 17(2b) EnWG are voluntary for both sides. The grid package currently under way discusses restricting this voluntary nature on the grid operator side. For the connection user, it remains in place in any case.

Does a ramp limit rule out balancing services?
FCR almost always. FCR requires full activation within 30 seconds, which means a ramp rate of 200% per minute. No FCA in the band of 1 to 20% per minute under discussion today meets that. For aFRR, the threshold is 20% per minute, because the full activation time is 5 minutes. Whether and how much aFRR volume below this threshold can still be prequalified depends on the design. Clarify this with your trading partner before you sign the contract. It also matters whether the ramp rate applies to ancillary services at all or only to spot trading.

Will I be compensated for the curtailment?
No. An FCA is a contractual advance limit, not redispatch. If you stay within the agreed limit, you have no claim to compensation.

Do I pay a lower Baukostenzuschuss (construction cost contribution for a grid connection in Germany) with an FCA?
Not at present. The BGH has upheld the Baukostenzuschuss for storage systems under the capacity price model. BVES and other associations are calling for an adjustment for restricted connections, but nothing has been regulated.

What is the difference between a static and a dynamic FCA?
Static means fixed time windows or an envelope fixed in advance. Dynamic means the permitted power follows the actual grid state, for example coupled to the grid feed-in of neighbouring wind and PV plants. Dynamic models curtail far less often but are more complex to operate. In our calculation, a dynamic, wind-coupled grid feed-in restriction cost 0.6% of annual revenues. For static envelopes, BET/IAEW and EERA report double-digit figures.

Sources

  • § 8a EEG 2023, § 17(2b) EnWG, introduced by the Solarspitzengesetz (German solar peak law of February 2025), BGBl. 2025 I No. 51, in force 25 February 2025
  • BNetzA (Germany's Federal Network Agency), decision BK6-25-325 of 30 March 2026 (grid connection of large-scale battery storage), assessment by Rödl & Partner
  • BGH, decision of 15 July 2025, EnVR 1/24 (Baukostenzuschuss for battery storage), press release No. 129/2025
  • Deutscher Bundestag, printed paper 21/7734 of 26 August 2026 (grid package)
  • BNetzA, AgNes (BNetzA reform of German grid fees towards capacity-based pricing) draft determination, August 2026
  • Transmission system operators, prequalification conditions for FCR, aFRR and mFRR (regelleistung.net), full activation times
  • minimum energy and inframind, Grid Connection Report Vol. 2, September 2026. Main source of the revenue figures
  • inframind GmbH, white paper “Full grids, unused reserves”, August 2026
  • BET Consulting and IAEW of RWTH Aachen for Green Flexibility, short study on flexible connection agreements, November 2025
  • EERA Consulting, Battery Beats: grid connection conditions (FCA), dynamic grid fees and their possible impact on standalone BESS revenues, 20 February 2026. Cross-validation and ramp reference points
  • Modo Energy, analyses of flexible connection agreements and power ramp rates in Germany, November 2025 to January 2026
  • The Mobility House Energy, FCAs and BESS: impact of flexible grid connections on revenues, July 2026. Carve-out practice
  • E.ON SE, press release 18 June 2026, and pv magazine, 19 June 2026 (FCA standard, 500 GW of enquiries, 25 GW of commitments)
  • HanseWerk / SH Netz, press release 28 April 2026 (first FCA for a biogas plant, Bioenergie Kropp)
  • BEE / Fraunhofer IEE / BBH, study on the oversizing of grid connection points, 12 April 2024
  • Neon Neue Energieökonomik (Lohr, Eicke, Hirth), short study “Grid-serving benefits of large batteries”, 1 September 2025, commissioned by ECO STOR GmbH. Sites Bollingstedt (SH, real) and Plattling (BY, hypothetical), redispatch data 2023 and 2024
  • Directive (EU) 2019/944 as amended by (EU) 2024/1711, Art. 6a

We use AI to support research, structuring and language editing. minimum.energy is responsible for the technical content, classification and approval. Figures, claims and project-specific statements are checked before publication.

Webinar recording: The robust FCA

Together with inframind, we show how a site becomes a power band and what that band costs in net present value (NPV), clause by clause. The Grid Connection Report Vol. 2 is available to download.