Key takeaways from this article:
- A separate connection makes the storage system a clearly defined trading asset, but the project is critical in terms of both grid connection and timing.
- In many cases the driver is simple: the existing connection lacks kW, and without kW, arbitrage stays small in the relevant time windows.
- The biggest risks are connection costs and time-to-grid, not the battery technology.
- Trading only works with clear restrictions, clean interfaces and performance reporting (throughput, availability, events).
- This scenario fits particularly well when trading is the priority and Multi-Use cannot (yet) be mapped cleanly at the site.
In the first article we showed that arbitrage for commercial businesses usually hinges on one basic question: separate connection (scenario A) or Multi-Use at the existing connection (scenario B). This second part focuses on scenario A: a dedicated grid connection or metering point just for the storage system.
It becomes relevant when the existing connection is tight on kW or you deliberately want to keep trading "clean" and separate. At the same time, it is the scenario in which connection costs and time-to-grid often shape the business case more than the battery itself. We cover what "separate" means in practice, which project and operating points you need to check early, and when scenario A is the better choice.
Why companies choose scenario A
Reason 1: The existing connection is the bottleneck (kW decides)
The most common reason is mundane: there is no capacity left at the site.
Depending on the strategy, arbitrage needs the ability to draw and feed in noticeable power in certain time windows. If the existing connection is already "full" because of production, refrigeration, compressed air or charge points, often only a residual window remains for the storage system in the relevant hours. The planned arbitrage operation then becomes heavily throttled operation, and the expected revenues shrink.
A clear look at kW vs. kWh helps here:
- kWh determine how long a storage system can run.
- kW determine whether it can use the price-relevant time windows at all.
A typical mistake in the preliminary assessment is to size only the amount of energy ("we need X MWh") and to realise too late that the connection capacity limits how the system can be operated ("but we are only allowed Y kW"). Scenario A is then simply the option to "get" the power you need, instead of looking for it at the existing connection where it does not exist.
Reason 2: Billing and demarcation should be as "clean" as possible
The more energy flows overlap at the existing connection, the sooner billing becomes a project within the project: PV, site load, storage charging, storage discharging, possibly feed-in, all in 15-minute intervals. If the storage system runs via a separate connection instead, allocation is simpler: the storage system has a clear input and output via its metering point.
This is particularly relevant if the organisation has little appetite for "metering concept discussions" and sees the storage system as a clearly defined investment that it wants to assess independently of site operation.
Reason 3: The trading set-up is external anyway (aggregator/schedule)
If it is clear from the start that an external partner will run the storage system in a market-driven way (arbitrage/trading, possibly schedules), the separation often fits the role logic well:
- The site provides space, grid connection set-up and defined restrictions.
- The trader/operator takes over dispatch, performance and reporting.
This often makes discussions in the project easier: less "who may touch which reserve and when?" and more "what availability do we guarantee and which restrictions apply?".
Cost and time logic: where the project can tip
A separate connection often makes trading "cleaner", but it almost always makes the project more connection-heavy. That is why business cases here rarely tip because of the battery technology, but because of two very down-to-earth things: (a) connection costs and (b) time-to-grid.
Connection costs & project effort: which blocks typically appear
Depending on size and existing situation, the following cost and effort blocks typically appear (not a complete list, but a realistic "EPC check"):
- Grid connection process: connection request, technical coordination, grid compatibility, possibly Baukostenzuschuss (construction cost contribution for a grid connection in Germany) or connection costs (depending on the grid operator's approach).
- Civil works & cable route: cable routes, crossings, surface reinstatement, construction site logistics.
- Substation/switchgear: depending on the power level, transformer/switch house, medium and low-voltage components, spare bays.
- Protection & control concept: protection relays, parameterisation, tests, possibly adjustments to existing protection concepts in the surrounding area.
- Metering/meter/communication: metering point(s), data connection, telemetry and control interfaces (also for trading).
- Engineering & documentation: detailed design, grid operator documents, test reports, commissioning documents.
- Construction & commissioning: coordination of trades, switchovers (if on the existing system), tests, acceptance.
The typical wrong assumption: "It's just a storage system." In connection projects the storage system is often the comparatively standardised part. The variance comes from the grid, infrastructure, construction and process.
Timeline & risks: why "time-to-grid" is the real business case lever
In trading-driven set-ups, the timeline is not just a project plan topic but a revenue risk: the longer the project takes, the stronger the effect of changes in the market environment and tied-up capital. Then there are the classics:
- Dependence on grid operator deadlines and coordination loops
- Lead times for switchgear/substations
- Construction windows at the site (access, safety briefings, restricted periods)
- Surprises underground (cable routing, crossings, existing infrastructure)
In practice this means: scenario A is attractive if you get a reliable answer early to two questions:
- Which connection solution is technically planned?
- What timeline is realistic for commissioning?
Decision template: what you should estimate reliably early on
Before diving into "revenues", it is worth having a short, honest sheet of paper (or a slide) with:
- Connection concept (power level, substation/switchgear, cable route)
- CAPEX ranges for the connection and infrastructure blocks
- Realistic project duration, including the grid operator path
- Worst-case assumptions (time and cost), not to be pessimistic but to avoid surprises
Operation & trading: how revenues really arise
Scenario A is often chosen because it is operationally more clearly separated. But "more clearly separated" does not mean "automatically profitable". What matters is how the storage system is run day to day and how well the operating strategy fits the technical and contractual boundary conditions.
Schedule operation / trading by an aggregator: what this means in practice
In many projects a trader/aggregator takes over operational optimisation. This is essentially a clear exchange:
- The site provides connection + asset + defined availability.
- The operator controls the storage system based on price and market signals and observes the restrictions.
To avoid friction, you should define three points very concretely:
- Availability windows: when may the storage system run, and when not?
- Restrictions: max. charge/discharge power, SoC limits, ramps, possibly local rules (switching frequency, safety shutdowns).
- Interfaces & responsibilities: who monitors, who intervenes in the event of a fault, how is performance reported?
EPCs in particular sometimes underestimate the "contract as part of the technology": if availability and restrictions are not described cleanly, that is exactly what gets argued about later in operation.
Revenue logic day to day: why performance measurement matters
The same applies to scenario A: arbitrage is not an "Excel button" but a performance question. In practice it pays to keep two levels apart:
- Revenue logic (what should happen?): charge in cheap time windows, discharge in expensive ones.
- Asset performance (what really happens?): how much throughput, how many cycles, which losses, which outages, which limitations?
If, for example, the storage system is frequently power-limited (connection, protection, requirements), operation can be "formally" correct but still fall short of expectations economically. That is why simple KPIs belong in every project report:
- Energy throughput (MWh)
- Number of cycles / equivalent full cycles
- Availability / downtime
- Curtailments/restriction events (why did it not run?)
Interfaces to the site (despite a separate connection)
"Separate" does not mean "no interfaces". Typical points you still need to clarify:
- Safety and operating rules at the site (access, shutdowns, emergency concepts)
- Grid-side requirements (protection, reactive power, telecontrol connection, depending on the connection)
- Communication: who has access to which data, how are events documented?
In practice the cleanest implementation is often the one where the site team and the operator agree on a simple rule: "What is normal operation, and what happens when something is not normal?"
{{use-case}}
When is this scenario the better choice?
Scenario A is not "better" than Multi-Use. It is different. And it fits particularly well when the bottleneck really is the connection and the target picture is clearly trading-driven.
"Fits better" if…
- the existing connection is tight technically or contractually and you cannot cleanly fit the required charge/discharge power at the site
- the organisation thinks of the storage system as an independent trading asset (clear operation, clear responsibilities)
- an external operator/aggregator is a given anyway and operation is to be market-driven
- you value clear metering and billing boundaries in the project and want to avoid "mixed operation" at the site
- the real levers at the site are not primarily in peaks, procurement or PV, but in trading
"Fits less well" if…
- the main levers are clearly on the site side (peaks, procurement, PV surpluses, flexible loads) and you want to actively realise this value. Multi-Use is then often the stronger approach
- connection costs and timeline are likely to be so large that they dominate the case
- you actually want integrated optimisation and the organisation and processes are already mature enough for it (data access, energy management system, clear target priorities). The separation then becomes less attractive
Typical mistakes (anti-patterns) with a "separate connection"
- Connection costs and construction effort underestimated: the storage system is ordered quickly, the connection infrastructure is not.
- Time-to-grid ignored: the business case is sensitive to delays, especially when revenues are market-driven.
- kW and kWh mixed up: lots of energy without sufficient power leads to a "nice storage system" with few usable price windows.
- Availability and restrictions not contractually precise: terms then get renegotiated in operation, usually to the detriment of performance.
- "Separate" interpreted as a free pass: site and grid restrictions remain real. They are just called something else.
EPC checklist (compact)
12 questions for the initial conversation / preliminary assessment
- What is the bottleneck today: connection capacity, transformer, protection, process?
- What power (kW) must the storage system realistically be able to deliver for arbitrage/trading to become relevant at all?
- Are there construction and cable route restrictions at the site (access, crossings, restricted periods)?
- At which voltage level will it be connected (LV/MV) and what does that mean for the substation/switchgear?
- Which grid operator processes can be expected (documents, tests, acceptance)?
- What does the protection concept look like, and who is responsible for parameterisation and testing?
- How is it measured (metering point, data access, telemetry), and who gets which data?
- Who is the operator (aggregator/operator) and which interfaces does it need?
- Which restrictions apply in normal operation (power, SoC, ramps, operating times)?
- What happens in the event of a fault (fallback, shutdown, responsibilities)?
- Which KPIs/reports are agreed (availability, throughput, event log)?
- Which goals are fixed (trading) and which are "nice to have" (site benefit), so that you can justify the architecture properly?
What should be in the quote
- Architecture decision clearly justified: why scenario A (and which alternatives were examined)?
- Project plan with critical path (grid operator, lead times, construction, commissioning)
- Scenarios (conservative/realistic/optimistic), not only for prices, but also for availability and project duration
- Sensitivities: connection costs, time-to-grid, power limits, efficiency/degradation, availability
If you are currently in the preliminary assessment and have to decide between a "separate connection" and "Multi-Use at the existing connection": we can structure this cleanly in 30 minutes based on connection data, load profile and target picture. Request a free demo now.
We use AI to support research, structuring and language editing. minimum.energy is responsible for the technical content, classification and approval. Figures, claims and project-specific statements are checked before publication.
Cross-market instead of arbitrage-only: How FCR and aFRR almost triple the net present value of a 10 MW BESS
10 MW grid connection, standalone BESS: arbitrage alone delivers a net present value of €6.3 million. With FCR and aFRR in the stack, it becomes €17.3 million, and a grid operator's ramping requirement can be quantified to the euro.
40,9 %
17.3 million
2.4 yrs
2,7×