Key takeaways from this article:
Since February 2025, new rules have applied to the grid feed-in of solar power. For commercial and industrial projects, they shift parameters that feed directly into the business case calculation.
At the same time, the legal situation is more in flux than it has been for a long time. Two procedures are running in parallel, and one of them targets the remuneration basis of every project that goes into operation from 2027. In the trade press, a Solarpaket II is also circulating, and many sources present it as adopted, although it is not.
This article separates three levels. What applies today. What is in a procedure and therefore belongs in your scenario. And what is purely an announcement.
What the Solarspitzengesetz regulates
Its official title is "Gesetz zur Änderung des Energiewirtschaftsrechts zur Vermeidung von temporären Erzeugungsüberschüssen", published in BGBl. 2025 I Nr. 51 and in force since 25 February 2025.
The trigger is measurable. According to the Statistisches Bundesamt, PV generated 70.1 billion kWh in 2025, which is 16.0% of domestic power production and a record since data collection began in 2018. On sunny middays, the systems generate more power than is consumed at the same time. The result is negative exchange prices. In 2025 there were around 573 hours of them, about six per cent of the year.
Until then, there was a perverse incentive. Operators received their fixed tariff even at negative prices and kept feeding in. Grid operators had to curtail, and all electricity customers bore the costs.
Zero payment at negative prices, with partial catch-up
If the Day-Ahead price turns negative, the payment entitlement for new systems from 2 kWp lapses from the first negative quarter-hour (§ 51 EEG). The previous waiting period of three or four hours no longer applies.
Under the compensation mechanism in § 51a EEG, the quarter-hours without payment are counted and added as extra months after the regular remuneration period ends. Important for your calculation: a reduced crediting factor applies to solar systems here. So only part of the lost payments is offset later, not the full amount.
For your model, this means two things. The present value falls, because the offset share is pushed back by around twenty years. And a remainder is lost for good. If you price the catch-up in as full compensation, your calculation is too optimistic. If you ignore it completely, it is too conservative.
The 60% limit does not hit every C&I project
It pays to look closely here, because this rule is regularly misapplied in practice.
According to the Clearingstelle EEG|KWKG, the limit of 60% of installed capacity applies to systems below 100 kW that have gone into operation since 25 February 2025. It applies until a smart metering system and control device have been installed and the first successful test of controllability has been completed.
The second part of the rule is the decisive one. It only affects systems assigned to the feed-in tariff or the tenant electricity surcharge (§ 9(2) EEG). If you assign the system to the market premium or other forms of Direktvermarktung, there is no obligation to limit feed-in.
In practice, this means a clear split:
| Project type | 60% rule | Zero remuneration at negative prices | Remote controllability |
|---|---|---|---|
| Under 100 kWp, feed-in tariff or tenant electricity surcharge | Applies until the smart metering system and control device are installed and successfully tested | Applies from 2 kWp | Mandatory from 25 kWp |
| Under 100 kWp, market premium or other Direktvermarktung (selling generated power via a direct marketer under the German EEG) | Does not apply | Applies | Mandatory |
| From 100 kWp | Does not apply | Applies | Mandatory |
Basis: § 9(2) EEG 2023 and Frequently Asked Legal Question No. 70 of the Clearingstelle EEG|KWKG. As of August 2026.
So if you mainly plan systems from 100 kWp, the 60% debate is largely irrelevant for you. It matters in the segment of smaller commercial roofs that stay on the feed-in tariff. Even there it is a transitional phase, and the project team influences its length through the metering technology itself.
Here is one more point that helps in customer conversations: the limit applies to output, not to volume. Only what exceeds 60% of maximum output is curtailed. Self-consumption is unaffected.
Metering technology and remote controllability
The obligation to install a smart metering system and control device applies from 7 kWp. For systems from 100 kWp and for all systems in Direktvermarktung, the remote control obligation continues unchanged (SMA on § 9 EEG).
Two things are often underestimated. First, the lead time at the responsible metering point operator. Register your requirement early. Second, connectivity: the smart metering system needs a mobile or broadband connection to receive control commands. At industrial sites in remote locations, this is not a given.
Without this technology, you also lose the entitlement to the catch-up under § 51a, because the lost quarter-hours cannot be properly recorded in the first place.
What really changes for C&I projects
The lever is not the 60% rule but the zero-remuneration hours. And they hit large systems harder than small ones, for three reasons.
They feed in large volumes. Unlike small self-consumption systems, a larger share of the generation from C&I roofs actually ends up in the grid. This is exactly the share affected by zero remuneration.
They are in Direktvermarktung anyway. This means the zero-remuneration rule applies immediately and without a transition window.
Their economic viability is calculated, not estimated. C&I systems are investment projects with return targets. If you do not model 573 zero-remuneration hours per year and the reduced crediting factor, you overestimate yields and only notice during operation.
The good news is not the size of the loss but the fact that you can control it. Unremunerated hours can be redirected into self-consumption or storage charging. If you plan for this from the start, you often come out better than before the change in the law, because surpluses are no longer given away.
Three levers in the design
1. Clarify the marketing route before sizing the storage system
From 100 kW, Direktvermarktung is mandatory. Below that, it is a decision with consequences, because the two routes lead to different storage strategies.
With the feed-in tariff, the self-consumption share counts. Flexible loads such as refrigeration systems, heat pumps or charge points are shifted to the midday hours or supplied via the storage system. In return, the 60% limit applies until the metering technology is in place.
With Direktvermarktung, this limit no longer applies, but market price opportunities come into play. Only here does the storage system turn from a pure PV buffer into an active revenue generator.
This decision is subject to a caveat, though, because the ongoing EEG amendment addresses exactly this point. More on that below.
2. Overplanting instead of curtailment
Where the 60% limit applies, the obvious solution is an appropriately configured inverter. The overplanting strategy is more interesting: install more PV modules than inverter capacity. The inverter limits the feed-in peak, and a DC-coupled storage system absorbs the surplus generation. The modules work at their maximum more often, without putting additional load on the grid.
3. Size the storage system from the load profile
There is no rule of thumb for the right storage size, and anyone who offers one has not looked at the load profile. Four variables determine the sizing: the surplus output at midday, the duration of the surplus windows over the year, the parallel demand from peak shaving, and the question of how much state of charge you reserve for which purpose.
Control matters just as much as size. With solar and load forecasts, the storage system discharges specifically before midday and creates room for the solar peak. Without this predictive control, it is full exactly when it is needed.
The mistake that costs the most return
If you design a storage system for peak shaving and add PV surplus buffering on top afterwards, you get a result that does not hold up in operation. Both applications draw on the same capacity, but at different times and with different urgency.
If you calculate sequentially, you first fix a peak shaving reserve and optimise the rest for PV. The result is systematically too small or too large, depending on which use case you calculated first. The optimal reserve for peak shaving depends on how often the storage system is filled at midday anyway. And the optimal PV buffer capacity depends on how much reserve peak shaving really needs. The two variables determine each other.
It only becomes clean when the optimisation solves both goals at the same time over the same 15-minute grid. The model then decides for each interval which benefit is greater, instead of inheriting a ranking that someone set beforehand.
We explain how the sizing logic works in detail in our article on strategy and sizing.
Operation: what a good EMS does at negative prices
The real optimisation happens during operation. On sunny weekends and public holidays in summer, exchange prices turn negative for a few hours. Without countermeasures, the system receives no remuneration. In Direktvermarktung (selling generated power via a direct marketer under the German EEG), it may even be actively curtailed, because the power cannot be sold by the marketer.
An energy management system has three levers.
Anticipate negative prices. Modern EMS read price forecasts from power exchanges or dynamic tariffs. If negative prices are foreseeable for the next day, the system deliberately discharges the storage system beforehand, so that it has absorption capacity in the critical window.
Shift loads. C&I businesses have flexible processes. Cooling systems can be pre-cooled, production steps brought forward, and power-to-heat converts surplus into usable heat. A kilowatt hour fed in without payment becomes a kilowatt hour that replaces grid consumption.
Use arbitrage. In Direktvermarktung, the EMS can take in additional grid electricity at strongly negative prices, store it temporarily and feed it back in when prices are positive.
Whether this pays off depends on three provisions. § 19(3b) EEG regulates which share of the discharged electricity counts as eligible EEG electricity and which as grid electricity. § 21 EnFG determines how levies are treated for the temporarily stored quantities. § 118(6) EnWG regulates the time-limited grid fee exemptions for electricity storage.
The framework for privileged treatment is in place, but how it works in practice on the grid fee side is not yet conclusively settled. Which quantities are cleanly separated under which metering condition is governed by the MiSpeL (German BNetzA rules for storage that charges both grid power and on-site renewable power) measurement procedure, which we break down in a separate article. Without a robust metering concept, the arbitrage case remains a model calculation.
A simplified worked example
Model case with disclosed assumptions, not a customer reference.
Assumptions: 200 kWp PV in Direktvermarktung, 200 kWh usable storage capacity, 100 kW charge and discharge power. A sunny Sunday in July, negative-price window from 12:00 to 14:00 at minus €50 per MWh. PV generation in the window is 300 kWh, Sunday base load is 40 kW, so 80 kWh. The energy charge for grid consumption including grid fees is 22 cents per kWh, round-trip efficiency is 90%.
Without EMS: The storage system filled up with PV power in the morning and cannot absorb anything more. 220 kWh go into the grid at zero remuneration.
With EMS: By 11:00, the system discharges the storage system to 30% via internal consumers, which creates 140 kWh of absorption capacity. Pre-cooling the cold stores ties up a further 40 kWh. In the window, 180 kWh go into the storage system and the process, and 40 kWh go into the grid.
Result: 180 kWh captured instead of 0, so 82% of the surplus. On Monday, the stored 140 kWh replace 126 kWh of grid consumption after efficiency losses, which is worth around €28. On top of that comes the part of the remuneration that would otherwise have been lost for good through the reduced crediting factor.
A single event therefore moves a modest amount. That is the honest finding. The lever comes from frequency, with 573 negative-price hours a year, and from the fact that the same control logic also acts on peak shaving and procurement all year round. Anyone who justifies a storage system with negative-price hours alone is selling a thin case.
Before you calculate your next quote
In the recording from 27 August, Felix, Leander and Leon show what the AgNes (BNetzA reform of German grid fees towards capacity-based pricing) draft from the Bundesnetzagentur (BNetzA, Germany's Federal Network Agency) means for storage projects and how to model the switch from the demand charge to the capacity charge. 45 minutes, calculated on a real storage system. Watch the recording
Would you rather run the numbers for your own site? Then book a short demo.
What is currently in the legislative process
EEG amendment: the fixed feed-in tariff is to end from 2027
On 29 July 2026, the Federal Cabinet adopted the government draft of the EEG amendment together with a grid connection package (assessment by ARQIS). On 14 August 2026, it was received as Bundesrat document 470/26. The Bundestag debated the draft in its first reading on 24 September 2026 (Bundestag document 21/7867), and the Bundesrat issued its opinion in the first round on 25 September 2026. The hearing in the Committee for Economic Affairs and Energy took place on 5 October 2026. The second and third readings have not yet been scheduled, and according to the trade press, completion is slipping into December (ZFK, 6 November 2026). Status as of 12 November 2026. What this means for projects commissioned in 2027 is covered in our article EEG amendment 2027: status, content and consequences for PV and storage.
The draft provides for ending the fixed feed-in tariff for new plants on 1 January 2027. Direktvermarktung becomes the standard case. For smaller plants, a time-limited transitional payment is planned, for a maximum of 36 months after commissioning. Anyone who wants to keep earning revenue for fed-in electricity must then switch to Direktvermarktung, or alternatively the grid operator takes the electricity without payment. Existing plants stay protected: anyone commissioned by 31 December 2026 keeps the promised tariff for the full term.
The tight timetable is driven by state aid law: the EU Commission's approval of the support scheme currently in force expires at the end of 2026.
Important: This is a government draft, not law in force. The Bundestag and Bundesrat must approve it, and the support provisions are also subject to state aid approval. Until the amendment enters into force, the EEG continues to apply in full.
What to do with this: Every project with a planned commissioning date from 2027 needs a second scenario without a fixed feed-in tariff. Not as a forecast, but as a range.
AgNes (BNetzA reform of German grid fees towards capacity-based pricing): the demand charge becomes a capacity charge
On 6 August 2026, the Bundesnetzagentur (BNetzA, Germany's Federal Network Agency) published the complete draft determination on the general grid fee system for electricity and started the final consultation (press release). Comments could be submitted until 18 September 2026. The determination is due to be issued in 2026, and follow-up determinations that add detail are planned for 2027.
Under the draft, the determination replaces the Stromnetzentgeltverordnung from 1 January 2029, and that regulation expires at the end of 2028. The core change: in future you pay for capacity rather than for load peaks. For storage projects, the draft also improves grandfathering.
This shifts the classic peak shaving business model and with it the optimal storage sizes. Every business case that runs beyond 2029 currently calculates with grid fees that will no longer exist in this form.
And what about Solarpaket II?
Very specific claims are circulating about Solarpaket II. It was supposedly adopted at the end of 2024 and has been in effect since 2025. Or it comes into force on 1 July 2026.
Neither is true. As of August 2026, Solarpaket II is a politically announced project with no adopted text and no date. Do not confuse it with Solarpaket I, which was adopted on 26 April 2024 and has applied since 16 May 2024.
In terms of content, it is meant to address four areas: less red tape for the grid connection, Energy Sharing, better storage integration and a gradual extension of Direktvermarktung (selling generated power via a direct marketer under the German EEG).
The difference from the EEG amendment matters in practice. The EEG amendment is before the Bundestag as a printed paper, has a concrete text and a procedure under way. It belongs in your calculation as a scenario. Solarpaket II belongs on your watch list.
What this means in practice
The Solarspitzengesetz (German solar peak law of February 2025) does not slow down commercial PV projects. It shifts where economic viability comes from. What decides is no longer the maximum feed-in volume, but how well a system absorbs surpluses, shifts them and uses them at the right time.
Three points for your next projects:
- First check which rule applies at all. System size and marketing form decide whether the 60 percent limit is relevant for your project.
- Do not count the catch-up under § 51a as full compensation. The reduced crediting factor belongs in the model.
- Calculate in scenarios, not in a single status. Law in force as the base, EEG amendment and AgNes as scenarios.
{{cta}}
We use AI to support research, structuring and language editing. minimum.energy is responsible for the technical content, classification and approval. Figures, claims and project-specific statements are checked before publication.
Grid-scale storage co-location: PV, green power storage system & trading BESS as a grid-supportive system
5 MWp ground-mounted PV as grid-scale storage co-location: how a green power storage system optimises PV revenues, and how a second trading BESS scales the net present value (NPV) from €563k to €3.15 million.
13,5%
6.5 yrs
3.15M
1.14M
Ready for quotes that actually hold up?
Bring an example project. In 30 minutes, we will show you how minimum energy transforms your pre-sales process.