2.500-Stunden-Regelung & peak shaving: reduce grid fees for C&I

Table of contents

More about the author

Dr.-Ing. Leander König-Kotzur

Managing Director Product

Go to author page
Go to Google Scholar profile

More about the co-author

Dr.-Ing. Felix Kullmann

Managing Director Customer Success

Go to author page
Go to Google Scholar profile

Share this post

Key takeaways from this article:

  • The 2.500-Stunden-Regelung under § 19 StromNEV reduces grid fees from utilisation hours ≥ 2,500 h and annual consumption ≥ 10 GWh per offtake point.
  • Peak shaving works twice over: it lowers the load peak directly and increases the utilisation hours in the calculation. Often this is the only way to reach the 2,500 h threshold at all.
  • Legal framework: § 20 EnWG, ARegV and § 19 StromNEV. Revenue shortfalls of grid operators are distributed nationwide through the § 19 levy.
  • Battery storage is the key lever, both for entering the scheme and for permanently lower demand charges afterwards.
  • Why this matters

    For commercial and industrial (C&I) customers, grid fees make up a considerable share of electricity costs. What counts is not only the energy consumed (kWh), but above all the maximum quarter-hourly demand measured (kW).
    This is exactly where the 2.500-Stunden-Regelung under § 19 StromNEV comes in: companies with consistently high electricity consumption (utilisation hours above 2,500 per year) can reduce grid fees significantly. In practice, peak shaving with battery storage is the key lever for realising these benefits.

    Basics: the 2.500-Stunden-Regelung

    • From utilisation hours ≥ 2,500 h (consumption ÷ highest load peak), a reduced grid fee applies.

    • Requirements:


      1. Annual consumption ≥ 10 GWh per offtake point

      2. Proof of at least 2,500 utilisation hours

    • Companies with an even load profile get relief, while sites with high load peaks pay more.

    Without reaching this threshold, you cannot apply for special grid fees.

    2.500 Regelung Peak Shaving

    How it links to peak shaving

    Peak shaving means cutting load peaks so that the maximum quarter-hourly demand falls.
    This has two direct effects:

    1. Access to the scheme: The utilisation hours rise in the calculation, so companies pass the 2,500 h mark.

    2. Direct cost reduction: The demand charge in the grid fees falls regardless of the scheme.

    Connection:

    • “We have an atypical load profile” → requirement for special grid fees.

    • “We reduce our highest load peak” → direct lever for cutting costs.

    {{cta}}

    Legal framework

    • § 20 EnWG, ARegV, § 19 StromNEV

    • Simultaneity function:


      • 0 h = max. simultaneity factor of 0.2

      • 2,500 h = inflection point

      • 8,760 h = simultaneity factor of 1

    The Bundesnetzagentur (BNetzA, Germany's Federal Network Agency) reviews and approves individual agreements. Revenue shortfalls of grid operators are distributed nationwide through the § 19 levy (2025: 1.553 ct/kWh).

    Calculating utilisation hours

    Utilisation hours [h]=Annual consumption [kWh]maximum quarter-hourly demand [kW]\text{Utilisation hours [h]} = \frac{\text{Annual consumption [kWh]}}{\text{maximum quarter-hourly demand [kW]}}Utilisation hours [h]=maximum quarter-hourly demand [kW]Annual consumption [kWh]

    • High maximum quarter-hourly demand = low utilisation hours

    • Peak shaving = smoothed load → more utilisation hours

    Battery storage as the key

    Grid-scale storage improves grid fees in two ways:

    • Enabling entry: Peak shaving lifts you above the 2,500 h threshold.

    • Cutting costs: Even after entering the scheme, a storage system permanently reduces the maximum quarter-hourly demand and with it the demand charge.

    {{use-case}}

    Conclusion

    The 2.500-Stunden-Regelung sets the framework, and peak shaving is the method for realising its benefits. Companies with high consumption and an even load can save significantly on grid fees this way, legally secure and technically scalable.

    Your next step

    With minimum.energy you simulate load profiles, tariffs and storage strategies in a single run, including proof for the 2.500-Stunden-Regelung.

    Book a live demo now

    We use AI to support research, structuring and language editing. minimum.energy is responsible for the technical content, classification and approval. Figures, claims and project-specific statements are checked before publication.

    Ready for quotes that actually hold up?

    Bring an example project. In 30 minutes, we will show you how minimum energy transforms your pre-sales process.

    Sign up once and stay informed

    Email distribution list

    Sign up once and stay informed

    On this list, we keep you up to date on upcoming webinars, trade fair appearances, new blog posts and glossary entries, as well as our brand-new monthly newsletter covering all product news.
    No items found.