EEG 2027 amendment: What pays off for commercial and ground-mounted PV

Table of contents

More about the author

Dr.-Ing. Leander König-Kotzur

Managing Director Product

Go to author page
Go to Google Scholar profile

Share this post

Key takeaways from this article:

  • Ground-mounted PV. 14 GW of tenders per year at a maximum value of 5.9 ct/kWh. The redispatch reservation in the grid package is still open.
  • Clawback for ground-mounted PV and systems from 200 kW. If the annual market value is above the applicable value or award value, the system pays back the difference. Anything it markets better than the average stays with it.
  • Market premium instead of feed-in tariff. The applicable value for rooftop systems is 6.2 ct/kWh, and the most recent annual market value for solar is 4.5 ct/kWh.
  • No payment at negative prices. In 2025 there were 575 hours with a negative spot price.
  • One feed-in cap for PV and storage. Rooftop systems from 25 to under 100 kW feed in at most 50 per cent of their PV output, storage included.
  • Brussels. Support payments for systems commissioned from January 2027 are expected to arrive late, but retroactively.

This week you are calculating a solar park with storage or a large commercial roof, commissioning in 2027. Which revenues do you enter?

As of 16 November 2026: the EEG amendment is not yet law. On 12 and 13 November, Union and SPD agreed in substance on changes to the government draft, but no legislative text is available yet. This article goes from large to small systems and shows what changes for economic viability.

Note on status: The information refers to the government draft (Bundestag document 21/7867) and, where stated, to reports on the parliamentary groups' agreement of 12/13 November 2026. The Bundestag can still change every point. Updated on 16 November 2026. Not legal advice.

Four levels you must not mix up

Only the law in force belongs in the calculation as the base case. Everything else is a scenario.

Law in force (base case). EEG 2023 with the Solarspitzengesetz (German solar peak law of February 2025), in force since 25 February 2025 and approved under state aid rules until 31 December 2026. The determination on MiSpeL (German BNetzA rules for storage that charges both grid power and on-site renewable power) by the Bundesnetzagentur (BNetzA, Germany's Federal Network Agency) of 1 October 2026. What the Solarspitzengesetz means for ongoing projects is covered in the article Solarspitzengesetz in practice.

Government draft (scenario). EEG amendment (Bundestag document 21/7867) and grid connection package (Bundestag document 21/7866), cabinet decision of 29 July 2026.

Parliamentary group agreement (further scenario). Changes by Union and SPD of 12/13 November 2026, so far known only from letters and media reports.

Demands (no figure). Bundesrat, associations, separating the parts relevant to state aid.

Where the procedure stands

The Bundestag wants to pass the amendment in the sitting week of 23 to 27 November. The Bundesrat can follow on 18 December at the earliest. Entry into force is planned for 1 January 2027.

The agreement is not complete. The Union wants to pass the EEG and the grid package only together, and there is still no agreement on the grid package, mainly because of the redispatch reservation. Several state energy ministers do not rule out the mediation committee. Under the draft, systems commissioned before 1 January 2027 stay under the existing law.

Ground-mounted PV and systems from 200 kW: market premium with repayment

Ground-mounted PV. The tender volume rises to 14 GW per year, and the maximum value stays at 5.9 ct/kWh. With clawback, negative prices and the redispatch reservation, the industry considers this too low. RWE is calling for at least 7 ct/kWh because, according to a Prognos study, levelised costs of electricity rise by up to 30 per cent. The innovation tenders for system combinations are dropped. They are replaced by resilience tenders with only 0.5 GW for ground-mounted PV.

Redispatch reservation. It is part of the grid connection package and affects ground-mounted PV and onshore wind. Grid operators can designate grid sections as capacity-limited for up to six years if more than 5 per cent of generation there was curtailed in the previous year. New systems there receive no compensation for curtailment of up to 20 per cent of their annual yield (wind: 18 per cent). Calculate the site with 0 and with 20 per cent uncompensated curtailment. A storage system at the grid connection point shifts part of this. How a restricted grid connection works out is shown in the article on the flexible grid connection agreement.

For ground-mounted systems and all systems from 200 kW, the market premium becomes a two-sided contract for difference. The government draft still set the threshold at 100 kW. If the annual market value is above the applicable value or award value, the system pays the difference back for every kilowatt hour fed in (refinancing contribution, § 21d). This also applies if it temporarily switches to other Direktvermarktung (selling generated power via a direct marketer under the German EEG).

What an operator markets better than the average stays with them. Only the gap between the annual market value and the applicable value is clawed back, not the individual revenue. The annual market value is the average of all solar systems. The repayment per kilowatt hour fed in is therefore fixed, regardless of what the individual system actually earns.

This works in both directions:

  • If you earn more than the solar average, for example with storage, east-west orientation or curtailment at low prices, you keep the full advantage.
  • If you earn less, you still repay the full gap in a clawback year.

Self-consumption and supply upstream of the grid are not affected at all. Under the contract for difference, the storage system therefore becomes the key lever: it lifts your own revenue above the average on which the repayment is based.

For your calculation, the upside from high-price years falls away. With the market values from 2021 to 2023, a system on 6.2 ct/kWh would have paid back for three years. If you permanently waive the market premium, you pay nothing back from the following year. The notification is a one-off and is possible until the end of the tenth year of support (§ 21e). Whether this exit option stays in place is still open.

How often the clawback applies depends on the threshold. For rooftop systems at 6.2 ct/kWh, a clawback year is rather unlikely on current trends: with every gigawatt of PV, the solar market value falls relative to the electricity price, and in 2025 solar power earned only around half of the average price. It is not ruled out. From 2021 to 2023, gas prices pushed the market value above it, and more storage systems will raise prices in the midday hours in future.

For ground-mounted systems the threshold is lower, because the award value is the benchmark there. In 2025 the awards averaged 4.7 to 4.8 ct/kWh, so close to the market value of 4.5 ct/kWh. Here the clawback is a real scenario.

{{newsletter-cta}}

Commercial rooftop under 200 kW

On a commercial rooftop, the market premium replaces the fixed tariff. In the draft, the applicable value for solar systems outside the tenders is a uniform 6.2 ct/kWh and falls by 1% every six months from 1 August 2027. The premium is the difference to the solar market value. If the market value is above it, there is no premium.

This is how the annual solar market value looked over the last five years (netztransparenz.de):

  • 2021: 7.6 ct/kWh
  • 2022: 22.3 ct/kWh
  • 2023: 7.2 ct/kWh
  • 2024: 4.6 ct/kWh
  • 2025: 4.5 ct/kWh

With the market values of the last two years, the premium would have been around 1.6 to 1.7 ct/kWh. From 2021 to 2023 there would have been none, and from 200 kW there would have been a repayment.

The solar market value is decoupling from the electricity price. In 2025 the average spot price was 8.932 ct/kWh, so solar power earned around half of that. Every kilowatt hour that moves from the midday peak into the evening is worth correspondingly more.

By system size:

  • From 200 kW: market premium with clawback, see the previous section.
  • 100 to under 200 kW: market premium without clawback (agreement), no cap, actual feed-in must be retrievable. Largely as today. Operators of full feed-in systems lose their bonus.
  • 25 to under 100 kW: market premium on 6.2 ct/kWh, feed-in cap of 50%. The midday peak has to go into self-consumption or storage.
  • 25 to under 50 kW: transitional payment of 5.2 ct/kWh for 36 months for commissioning in 2027. According to reports on the agreement, the grid operator also purchases the power at the annual market value. Simple marketing, hardly any premium.

In quarter hours with a negative spot price, there is no payment (§ 51). The support period is extended to compensate, by a factor of 0.5 for solar. In 2025 there were 575 hours with negative prices, mostly when PV is feeding in.

From 25 kW, the grid operator must be able to control the system remotely. The Direktvermarktung contract sets a price above which the system is curtailed. The bonus for full feed-in is dropped. The basics of both forms of sale under current law are in the article Feed-in tariff vs. Direktvermarktung.

The most important constraint up to 100 kW: a cap for PV and storage

New rooftop systems may permanently feed in at most 50% of their installed PV capacity at the grid connection point (§ 9(2b)). The cap applies to rooftop systems under 100 kW, and after the agreement between the parliamentary groups only from 25 kW. From 100 kW and for ground-mounted systems it does not apply. From 100 kW, however, actual feed-in must be retrievable. For a roof with 80 kWp, that is 40 kW.

The cap applies to everything that feeds in behind the grid connection point, including the storage system. It is measured solely against the PV capacity. PV and battery share the same 40 kW.

For your calculation, this means:

  • At midday, the PV uses up the cap. The storage system can absorb the peak, but cannot feed in anything additional.
  • In the evening and at night, at most the cap is available to the storage system. Discharge power above 50% of the PV capacity only helps self-consumption, not grid feed-in.
  • Arbitrage with grid electricity under MiSpeL (German BNetzA rules for storage that charges both grid power and on-site renewable power) therefore does not grow linearly with storage size. It hits the same cap as the PV.
  • If you calculate separately, first the curtailment and then the storage revenue, you overestimate the grid feed-in revenue.

How much the cap costs depends on the load profile. A business with a high midday load rarely feeds in more than half of the PV capacity anyway. In that case, the cap alone does not justify a storage system.

The storage system: three tasks, one state of charge, one cap

The draft aims for solar systems to be built with storage from the start as a rule in future. Behind the meter, the storage system takes on three tasks at the same time:

  1. It absorbs the PV output above the feed-in cap.
  2. It shifts feed-in out of quarter hours with a negative price.
  3. It additionally charges grid electricity via the separation option in the MiSpeL determination, without losing the entitlement to support. Until the end of September 2027, this requires the consent of the grid operator and the metering point operator, and the power fed in must run in a separate balancing group.

These tasks compete for the same state of charge and the same feed-in cap. A storage system that charged cheap grid electricity in the morning can no longer absorb curtailed PV at midday. And what it feeds in during the evening counts against the same 50% of PV capacity. The right size and discharge power therefore only follow from a joint optimisation across all quarter-hours of the year. For background on the separation option, see the article on the MiSpeL (German BNetzA rules for storage that charges both grid power and on-site renewable power) determination, which still describes the working position before the decision.

Ground-mounted sites have no cap, but two other drivers: negative prices without payment and, in a congested area, uncompensated curtailment. Both favour a storage system at the grid connection point, but you can only quantify them site by site.

Brussels: Funding is likely to arrive later, but retroactively

The new funding rules may only be applied once the European Commission has approved them. The existing approval expires on 31 December 2026, and time is tight for the EEG 2027 until then.

For systems commissioned in early 2027, this means the entitlement arises, but payment follows approval. We consider retroactive coverage likely. For the EEG 2021, approval only came on 29 April 2021, four months after entry into force, and the law applied from 1 January. The Stiftung Umweltenergierecht also assumes that an approval can take effect retroactively.

In the calculation, this is mainly a liquidity issue: for the first half of 2027, plan for a few months of delayed payment, not a loss of revenue. It is not entirely free of residual risk: the premium from Solarpaket I for commercial roofs has been waiting for approval since 2024.

What is still open politically

  • Redispatch reservation. The SPD wants to remove it, the Ministry for Economic Affairs is holding on to it. As long as it is open, the EEG is held up too.
  • Ceiling for ground-mounted PV. The industry is asking for more than 5.9 ct/kWh. The draft does not provide for this so far.
  • Details of the agreement. We only know the level and term of the remuneration below 25 kW and the purchase by the grid operator up to 50 kW from reports, not from a legal text.
  • Bundesrat. It had called for the 50% cap to be removed and can call the mediation committee. The BEE is asking for the time-critical parts of the EEG to be brought forward.

What you can do now

  • Commissioning before 1 January 2027 secures the existing rules. For later projects, calculate the draft as a scenario alongside the current legal position and state in the quote which version it is based on.
  • Ground-mounted and from 200 kW: Cap revenues from high-price years at the applicable value. Self-consumption, PPAs and additional storage revenues remain unaffected. Check the grid status of the site and calculate the redispatch reservation at 0 and 20%.
  • 100 to 200 kW: Compared with today, this band changes least: market premium without clawback and without a feed-in cap. Only full feed-in systems lose out, because their higher applicable value falls away. Compared with the government draft, the segment avoids the clawback.
  • Commercial roof, 25 to 100 kW: Calculate the cap for PV and storage together. Size the discharge power of the storage system for grid feed-in at no more than 50% of PV capacity. Anything above that is carried by self-consumption alone.
  • Liquidity 2027: For commissioning in the first half of the year, plan for a few months of delayed payment.
  • Operation: Control against four signals: feed-in cap, the price threshold from the contract for Direktvermarktung (selling generated power via a direct marketer under the German EEG), negative quarter-hours and, where used, the MiSpeL separation in the metering concept.
  • Communication: In customer conversations, keep the draft, the agreement and the law in force clearly apart.

In minimum energy, you calculate self-consumption, Direktvermarktung, feed-in cap, MiSpeL separation option and arbitrage as one optimisation problem and set scenarios side by side. The software cannot tell you which version the Bundestag will adopt. That is why the draft belongs in the calculation as a scenario, not as an assumption.

We will update this article as soon as the Bundestag has decided.

{{cta}}

Sources: Federal Government bill for the EEG 2027, Bundestag printed paper 21/7867 of 7 September 2026. Grid connection package, Bundestag printed paper 21/7866 of 7 September 2026. Opinion of the Bundesrat and counter-statement of the Federal Government, Bundestag printed paper 21/8298. Stiftung Umweltenergierecht, opinion for the hearing, committee document 21(9)376, and Würzburg Reports No. 62 of 29 September 2026. BNetzA (Germany's Federal Network Agency), MiSpeL determination, ref. 618-25-02. Bundestag, hib 692/2026 on the grid connection package. BEE, position paper on the redispatch reservation, 14 October 2026. ZfK, "EEG and grid package slip to December", 6 November 2026, and Energiegesetze-Ticker. Cleanthinking, agreement between the parliamentary groups on the EEG 2027, 14 November 2026, with reference to Table.Briefings and top agrar of 13 November 2026. Annual market values for solar: netztransparenz.de, via BSW-Solar and Rödl & Partner. Negative hours 2025: DGS based on energy-charts.info. BNetzA, results of the ground-mounted tenders 2025. top agrar and RWE on the ceiling for ground-mounted PV. All information as at 16 November 2026.

We use AI to support research, structuring and language editing. minimum.energy is responsible for the technical content, classification and approval. Figures, claims and project-specific statements are checked before publication.

Webinar: EEG 2027

What is changing and what it means for renewables and storage. Felix and Leon put the status of the legislative process in context and show how to recalculate PV and storage with a refinancing contribution.

Sign up once and stay informed

Email distribution list

Sign up once and stay informed

On this list, we keep you up to date on upcoming webinars, trade fair appearances, new blog posts and glossary entries, as well as our brand-new monthly newsletter covering all product news.