Key takeaways from this article:
- Each kilowatt hour fed in from a storage system is either eligible for the market premium or eligible for netting, never both. Models must calculate and compare both paths in parallel, not add them.
- Netting is done per calendar month, and the choices you make (option, metering concept, priority allocation) are binding for at least one calendar year. MiSpeL is a sizing topic, not a billing topic.
- The modelled case shows what this is worth: the same 2 MWh commercial and industrial (C&I) storage system raises its net present value (NPV) from €287,000 to €762,000 under MiSpeL, factor 2.7, on a conservative calculation.
- The second case shows what MiSpeL makes possible: three parties monetise 336 kW of unused grid connection capacity, with a benefit of €103,159 in the first year, and the sum of the perspectives reconciles to the euro.
- The determination has been adopted since 1 October 2026, but the calculation here is based on the working draft of 5 August. Until 30 September 2027 it applies only with the consent of the grid operator and the metering point operator, and the grid fee effect remains subject to AgNes (BNetzA reform of German grid fees towards capacity-based pricing). MiSpeL belongs in the calculation as a scenario, not as an assumption.
Arbitrage behind the meter becomes possible under regulation, as the Bundesnetzagentur (BNetzA, Germany's Federal Network Agency) determined the calculation rules on 1 October 2026. Two modelled cases show what that is worth: the same storage system raises its net present value (NPV) by factor 2.7, and a three-party deal unlocks 336 kW of unused grid connection capacity. If you want the numbers, you first need to understand the foundation.
Note on status: On 1 October 2026 the Bundesnetzagentur adopted the MiSpeL determination (file ref. 618-25-02, operative part with reasoning plus annexes 1 and 2). This article is based on the working draft of 5 August 2026. Individual provisions may differ in the final version. Information as of 21 September 2026, procedural status updated on 12 November 2026.
What applies today: three options in the law, but only one works
The legal basis has been in place since the Solarspitzengesetz (German solar peak law of February 2025). § 19(3) EEG covers the case where electricity is temporarily stored before grid feed-in and opens up three routes. The rules apply accordingly to charge points that can be used bidirectionally.
The exclusivity option (§ 19(3a) EEG) already works today: the storage system takes up only renewable electricity, so the storage grid feed-in remains eligible for support. The price is steep. If you store even one kilowatt hour of grid electricity, the storage grid feed-in loses its eligibility for support for the whole calendar year. That is exactly what has blocked Multi-Use with grid electricity to this day.
The separation option (§ 19(3b) EEG) allows mixed use. The entitlement applies to the share that is determined and evidenced in line with a determination under § 85d EEG. So the legislator has opened the door but delegated the key to the BNetzA. Without a determination, the calculation rule is missing.
The flat-rate option (§ 19(3c) EEG) applies to setups with solar systems up to 30 kWp and caps the entitlement at 500 kilowatt hours per kilowatt and calendar year. It also needs the determination, plus state aid approval from the European Commission.
In parallel, § 21 EnFG governs the levy privileges: grid electricity that is purchased deliberately, stored and fed back in should not be charged levies like final consumption. This mechanism also needs the evidence rules of the determination.
What is in the procedure: file ref. 618-25-02, from key points paper to working draft
The MiSpeL procedure (market integration of storage systems and charge points) has been running since 31 July 2025 at the BNetzA's renewable energy unit, not at a ruling chamber. If you look for a ruling chamber file number, you will not find one. The file reference is 618-25-02.
The sequence so far: on 18 September 2025 the key points came as a consultation draft, and by 24 October 2025 more than 60 statements had been received. On 5 August 2026 came the working draft, made up of the operative part, annex 1 (separation option) and annex 2 (flat-rate option). It is explicitly not a new consultation but early market information. The operative part provided for publication on 1 October 2026, and on that day the BNetzA adopted the determination. The BNetzA has scheduled a workshop on the determination for 2 October.
Compared with the key points, decisive things have changed. The most important change for modelling: netting is now done per calendar month instead of over the year. And the working draft now also covers setups without a subsidised renewable plant, from co-located storage systems to pure grid storage systems. The result is a set of rules with eleven case constellations and 44 formulas in the separation option alone.
The separation option: quarter-hour resolution, purely computational, with storage priority
Annex 1 makes clear that nothing is physically separated. The allocation is made "purely by calculation on the basis of share considerations", using quarter-hourly measured values that comply with metering and calibration law. Depending on the setup, this takes several metering points: Z1 at the grid connection point, Z2 for the storage system and charge point, and in one scenario Z3 for the storage system alone. Annex 1 sets no capacity threshold, so the separation option is open to installations of any size.
The sharpest rule is storage priority: simultaneous grid consumption is treated as charged into the storage system first, and simultaneous storage generation as fed into the grid first, expressed as taking the minimum for each quarter hour. Charging from the grid at the same time as generating your own power is therefore expensive, because it shifts volumes from the support-eligible pool into the netting-eligible pool and vice versa.
Four calculation rules determine the business case:
1. Every kilowatt hour is either supported or netted. Never both.
The formulas deduct the support-eligible renewable storage generation from the storage generation fed into the grid. What remains is eligible for netting. The market premium and the levy advantage compete for the same volumes. A model has to calculate both paths in parallel and compare them, not add them up.
2. Netting is done per calendar month.
Surpluses from one month expire. Sites with seasonal profiles systematically lose out compared with an annual view. If you calculate with annual totals, you overestimate the levy advantage.
3. Efficiency is a calculation variable, not a datasheet value.
In the basic case with a renewables installation and a storage system, efficiency is derived monthly from the measured values. As soon as a bidirectional charge point is involved, a flat 0.85 applies. If you actually run at 90%, you settle differently from how you operate. For fleets, the deduction for electricity charged elsewhere also applies: what is charged elsewhere and fed in here counts neither for support nor for netting.
4. Negative prices cut support, and in the flat-rate option netting too.
Quarter hours with an applicable value of zero do not count towards the market premium, in both options. The flat-rate option goes further: there, only grid feed-in in quarter hours with a non-negative spot price is eligible for netting. Both time series belong in every model.
On top of that come options with a one-year lock-in. The choice of option applies per feed-in point, in full or not at all. If you leave out the separate storage meter in a setup with a storage system and charge point, you lose the loss privilege completely, and if you have installed more precise metering technology, you may no longer use the simplified formula sets. Existing installations on the monthly market value must switch to the annual market value. And for companies under the Besondere Ausgleichsregelung, netting is worth little: it is applied at the lowest levy value of the year, in the BNetzA's (Germany's Federal Network Agency) worked example 0.2 instead of 1.4 cents per kWh. The authority itself calls the monthly determination there "hard to oversee" with "looming circular references" (Annex 1, section 9.3.1).
How to set up the metering concept and Multi-Use at an existing grid connection in practice is covered in our playbook article MiSpeL (German BNetzA rules for storage that charges both grid power and on-site renewable power) and separation in mixed operation. This article sticks to the procedural status and to the question of what the rules do to the net present value (NPV).
The flat-rate option plays practically no role for commercial projects. It ends at 30 kWp of solar capacity, has no loss privilege, has an indifference band that is neither supported nor netted, and is entirely subject to the EU Commission's state aid reservation. If you plan commercial and industrial (C&I) storage systems, you end up with the separation option.
What MiSpeL is worth: the same storage system, calculated twice
Before we get to new business models, here is the sober question: what is Multi-Use actually worth for a perfectly ordinary C&I storage system? To find out, we calculated the same storage system twice in minimum energy against the same baseline. It is a model case, not a customer reference, and the assumptions are open.
A commercial site in Bochum with 750 kWp of PV and around 1.2 GWh of annual demand is assessing a storage system with 2,000 kWh and 1,000 kW. The investment is €500,000, calculated over 20 years at 8% cost of capital. Scenario 1 is without MiSpeL privileges: self-consumption, peak shaving, procurement optimisation and spot trading, but the trading electricity bears full grid fees and levies. Scenario 2 calculates the same applications in a MiSpeL-compliant way, with cleanly separated electricity accounts for green electricity, grid electricity and trading electricity.
Even without privileges, the storage system already pays off solidly: €80,000 savings in the first year, an NPV of €287,000 and a payback period of 6.3 years. The charges on the trading electricity do, however, cap trading at around 177 MWh per year. MiSpeL-compliant, the trading volume rises to 324 MWh, trading revenues grow from €62,000 to €150,000 per year, the annual savings to €132,000 and the NPV to €762,000, with a payback period of 3.8 years. That is a factor of 2.7 in NPV, with the same storage system, the same investment and the same use cases.
More important to us than the factor is how it comes about: deliberately on the conservative reading. In the scenario, only the energy charge is reimbursed, and the trading electricity still counts towards the annual peak load and therefore the demand charge. You could calculate more aggressively. We do not, as long as the grid fee side of MiSpeL is a transitional arrangement. The full calculation with both scenarios and the link to the design in the platform is in the use case One storage system, all revenues: the same storage system with and without MiSpeL.
What MiSpeL makes possible: three parties, one storage system, 336 kW of unused grid connection
The second model case shows a setup that simply would not exist without the separation option. Here too: platform calculation, not a customer reference.
A C&I site with 750 kWp of PV and 1,000 MWh of annual electricity demand has a grid connection of 750 kW, and the actual peak load is 413.7 kW. 336 kW of connection capacity is paid for and sits idle, while BESS investors often wait years for their own connection points. On top of that, 105 MWh of PV electricity is curtailed per year. A third-party storage system that charges grid electricity behind this meter and feeds it back in previously fell outside the exclusivity option. With the separation option, exactly this setup works.
The site was calculated with three parties, each with its own calculation: a BESS investor who finances the storage system, the site, which contributes space and unused connection capacity, and a direct marketer with a revenue share in the trading revenue. Six applications were optimised simultaneously, from procurement through atypische Netznutzung (atypical grid usage under § 19(2) StromNEV, reduced grid fees for shifting load out of HLZF) to arbitrage. Two constraints decide the outcome: the connection capacity is a hard limit (the optimal storage system has 764 kW, which together with the load is more than the connection allows, and the optimiser decides per quarter hour), and MiSpeL separates the volumes (support-eligible or netting-eligible, netted monthly, both paths in parallel).
The optimal design is 1,528 kWh and 764 kW with an investment of €351,527, which corresponds to €230 per kWh as the cost assumption of the model calculation. The result, by perspective:
The site invests nothing. Its running energy costs fall from €110,155 to €62,042 per year, down 44%. The grid-fee-relevant capacity drops by 59%, even though the connection is now physically used up to 750 kW, because the charging windows are optimised against the HLZF (high-load time windows set by the German grid operator). Curtailment falls from 105 to 30.2 MWh per year. Net present value (NPV) over 20 years: €472,383.
The investor contributes the full €351,527 and gets something that is hard to buy on the market: an immediately available connection point, without a Baukostenzuschuss (construction cost contribution for a grid connection in Germany), without a grid compatibility check, without a waiting time. Arbitrage revenue is €56,742 per year, the internal rate of return is 12.8%, the payback period is 7.0 years and the NPV is €132,854.
The direct marketer provides market access and trading without any investment of its own and receives a revenue share of €3,171 per year, NPV €31,132.
The total adds up to the euro: €103,159 of benefit in the first year, an NPV of €636,369, and from the project's perspective a 28.7% internal rate of return with a payback period of 3.4 years. That is the real point: a project that returns 12.8% from the investor's perspective returns 28.7% from the project's perspective, because two thirds of the benefit accrue to the site and the marketer. If you calculate only one perspective, you negotiate with the wrong number. The full three-perspective calculation is in the use case MiSpeL BTM with three stakeholders: the free grid connection as a business case.
Our position: calculate conservatively, optimise simultaneously, name the caveats
At minimum energy, we see MiSpeL (German BNetzA rules for storage that charges both grid power and on-site renewable power) as the most important step towards market integration of storage systems in years. That is exactly why we say what we see critically and how we calculate with it.
The direction is right, but three points remain critical. Monthly netting penalises seasonal profiles without any visible benefit to the system. For companies in the Special Equalisation Scheme, netting is devalued to one seventh, and the Bundesnetzagentur (BNetzA, Germany's Federal Network Agency) itself calls its own system there "hard to oversee". And a rulebook with 44 formulas shifts complexity onto those who build projects. You can welcome that and still name it.
We calculate MiSpeL as a scenario, not as an assumption. Both model cases above include a base case without MiSpeL, and we calculate the grid fee side under the conservative reading, because the working version itself marks it as a transitional provision. A business case that only holds under the aggressive reading is not a business case. If you justify storage solely with MiSpeL privileges, you are selling a thin business case, and this audience notices.
We optimise simultaneously because the determination requires it. The storage priority offsets the subsidy path and the trading path within the same quarter-hour, the connection capacity caps charging and load at the same time, and the either-or rule couples the market premium to the levy advantage. If you calculate these applications one after another in tables and add them up, you get figures that occur in no operating year. In minimum energy, the MiSpeL allocation rules therefore run as constraints within one optimisation, at quarter-hour resolution and reproducible.
And we also state the uncomfortable figures. In the three-party case, the site's emissions fall by 14%. On the investor's account, arbitrage charging creates 4,100 kilograms of new CO2 equivalent, and net the project stays at minus 12%. Arbitrage behind the meter is a business model, not a climate protection argument. This kind of transparency is exactly why you can believe the other figures.
Timeline, caveats and the AgNes (BNetzA reform of German grid fees towards capacity-based pricing) exposure
Three caveats are explicitly stated in the working version, and they belong in every project decision.
The transition caveat: Until 30 September 2027, application requires the consent of the grid operator and the metering point operator. In the first year, applicability therefore depends on the cooperation of two third parties, with no enforceable right to it. If you are planning for 2026 and 2027, talk to the grid operator early.
The state aid caveat: The flat-rate option applies only after state aid approval by the EU Commission. No date for this is known.
The AgNes exposure: The effect of MiSpeL on grid fees runs through the reference in § 118(6) sentence 3 EnWG, and Annex 1 explicitly calls this referencing provision a transitional provision that can be replaced by the new grid fee system AgNes (section 2.2). The AgNes draft has been available since 6 August, and the consultation deadline ended on 18 September. For storage systems, this means in concrete terms: from 2029, the draft introduces a capacity fee of around €5 per kilowatt per year, and only existing assets and projects with a final investment decision by the end of 2026 keep the grid fee exemption under § 118(6) EnWG. What the draft changes in detail is covered in our article Grid fees 2029: what the BNetzA draft means for storage projects. For your models, this means: grid fees belong in the calculation as a scenario, not as a constant.
Our conclusion: calculate first, then commit
MiSpeL solves a real problem. The exclusivity option blocked Multi-Use for years, and now arbitrage with a levy advantage becomes possible in a regulatorily clean way. The two model cases show the range: for a standard commercial and industrial (C&I) storage system, it is about a factor of 2.7 in NPV, and at a free grid connection, constellations become viable that did not exist before. The price is a rulebook that moves the most important economic decisions to the start: choice of option, metering concept, priority allocation, all with a commitment of at least one year.
None of these questions can be answered across the board. Whether the separation option is worth the additional meter, whether the levy argument holds with your customer, how the connection restriction and the volume separation influence each other: that depends on the load profile, the storage size and the price scenario.
If you want to see what this looks like on a real project: the recording of our webinar on MiSpeL-compliant storage planning shows the complete path. And if you want to calculate your own business case, book a demo.
Frequently asked questions about the MiSpeL determination
What is the MiSpeL determination?
MiSpeL (market integration of storage systems and charge points) is a determination by the BNetzA under § 85d EEG that regulates how storage systems and bidirectional charge points can combine the EEG market premium and levy privileges under § 21 EnFG. The determination of 1 October 2026 provides for two routes: the meter-accurate separation option and the flat-rate option for solar systems up to 30 kWp.
When does MiSpeL come into force?
The BNetzA adopted the determination on 1 October 2026. Until 30 September 2027, application is only possible with the consent of the grid operator and the metering point operator. The flat-rate option additionally requires state aid approval by the EU Commission.
Can I combine the market premium and the levy exemption?
At the same site, yes. On the same kilowatt hour, no. Every storage kilowatt hour fed in is either eligible for support or eligible for netting. The split results by calculation from the formula sets of the determination, not from a free allocation.
Does the separation option also apply to large storage systems?
Yes. Annex 1 sets no power threshold, so the separation option is open to systems of any size. It also covers setups without a subsidised renewable energy plant, from co-located storage systems to pure grid storage systems. Only the flat-rate option is limited to solar systems of up to 30 kWp.
What does MiSpeL (German BNetzA rules for storage that charges both grid power and on-site renewable power) deliver economically?
That depends on the individual case and cannot be given as a single figure. In our two model cases, the net present value (NPV) of a 2 MWh commercial and industrial (C&I) storage system rises from €287,000 to €762,000 through the MiSpeL-compliant calculation. A three-party setup at a free grid connection generates a benefit of €103,159 in the first year. Both are platform calculations with disclosed assumptions, not customer references.
Sources: BNetzA, determination proceedings on the market integration of storage systems and charging points (MiSpeL), ref. 618-25-02: key points of 18 September 2025, working draft of 5 August 2026 (operative part, Annex 1 separation option, Annex 2 flat-rate option), proceedings page with workshop date 2 October 2026, determination of 1 October 2026 with press release and background paper of the same day. § 19(3), (3a), (3b), (3c) and § 85d EEG. § 21 EnFG. § 118(6) EnWG. BNetzA, Grand Ruling Chamber for Energy, AgNes (BNetzA reform of German grid fees towards capacity-based pricing) draft determination of 6 August 2026, ref. GBK-25-01-1#3, consultation deadline 18 September 2026. Model cases: platform calculations from minimum energy (use cases "One storage system, all revenues" and "MiSpeL BTM with three stakeholders"), not customer references. Section references relate to the respective draft version and may shift in the final version. This is not legal advice.
We use AI to support research, structuring and language editing. minimum.energy is responsible for the technical content, classification and approval. Figures, claims and project-specific statements are checked before publication.
C&I (commercial and industrial): one storage system, all revenues. The same storage system with and without MiSpeL
A commercial site with 750 kWp of PV is assessing a 2 MWh storage system. The same storage system, calculated twice: with full grid fees and levies on the trading electricity, and MiSpeL-compliant. The net present value (NPV) rises from €287,000 to €762,000.
132k
762k
3.8 yrs
2,7×
Webinar recording
Our webinar recording shows how to model behind-the-meter storage in minimum energy in line with MiSpeL. It uses a real project, straight from the software, and is the practical complement to this article.