04.12.2026

lcmd onsiteOur next webinar

Grid connection in 2031, charging park in 2027: how you bridge the gap with a storage system and still make the numbers work
minimum.energy
/
Case Studies
/
SEINE Batteriesysteme
Case Study

From storage manufacturer to energy service provider: how SEINE Batteriesysteme sells products with minimum energy that did not exist before

SEINE builds storage systems for mid-sized businesses and industry and controls them with its own EMS. Technically, the team has always been able to do Multi-Use. With minimum came depth in energy economics, and with it products that did not exist before.

"With minimum, we really go into depth. That enables us to deliver a better result for the customer. And it is an additional product that we can sell."

Johannes Rosenthal

Johannes Rosenthal

Business Development ESS, SEINE Batteriesysteme

Segment

Storage system manufacturer and system provider for mid-sized companies and industry, with its own EMS (SEINE OS)

Region

All of Germany

Sales

Business Development ESS and technical management calculate in minimum. Contacts at the customer: energy procurement, site management, technical management

Project focus

C&I battery storage in Multi-Use (self-consumption, peak shaving, atypische Netznutzung (atypical grid usage under § 19(2) StromNEV, reduced grid fees for shifting load out of HLZF)), AC connection, certification, planning process with the grid operator, procurement optimisation

With minimum since

May 2025

Case study key facts

+50 %

larger orders from industrial customers

~25 MWh

in around 30 ongoing storage projects, designed with minimum

1 kW

deviation between design and operation in a completed project with a 6.3 MW load peak
01 · The starting point

Technically strong, but selling below its value

Technology has always been SEINE's strength. Its own EMS, SEINE OS, could already run the Multi-Use approaches before minimum: self-consumption, peak shaving, atypische Netznutzung (atypical grid usage under § 19(2) StromNEV, reduced grid fees for shifting load out of HLZF), procurement optimisation. In operation, the storage system did what it was supposed to. What was missing was a detailed view of economic viability.

“We were always very strong technically. Our control system could already model the Multi-Use approaches before minimum. But we could not look at them from an economic viability angle. That was our biggest pain point.”

Jan Sievert, Technical Manager, SEINE Batteriesysteme

The quoting process was quick and narrow. A customer enquires about a storage system, the load profile arrives, the old tool says “that would make sense”, and a week later the quote is ready. For the storage system. Not for what is needed around it.

And the design looked at one use case after another: self-consumption, peak shaving, in parallel, never in combination. Whether the storage size was also enough for procurement optimisation, whether to go bigger for it or give up self-consumption, could not be calculated against each other.

The problem was not the system but the calculation. Technically and economically, the SEINE system was often the strongest business case, but the calculated ROI fell short of reality. SEINE sold itself short. And the storage system remained a product you deliver, rather than a service you sell.

02 · The decision

The added value lies in the depth

Every user unlocks the value of minimum in their own way. B&W Energy runs the calculations live in the customer meeting and gains speed. SEINE takes a different route. When the team started with minimum in May 2025, the aim was to finally bring the depth the EMS had long had in operation into design and consulting too. At SEINE, minimum stands for product innovation.

“We want to show the customer the electrification process and support them through their transformation. That does not happen on the side during an on-site visit.”

Jan Sievert, Technical Manager

This attitude shapes the process. SEINE does the calculations calmly during project planning. “We want to give the customer a perfect result and not make promises we cannot keep,” says Johannes. Because it is about more than a storage system: it is about the electrification pathway of a site, with everything that goes with it.

For this, SEINE has developed its own approach: the results are exported from minimum and turned into a detailed energy economics potential analysis that meets the customer where they are. “One only knows self-consumption, another is already fully into procurement. That is a huge difference.”

The result: customers no longer get just a storage system today, but the whole project. “Before, it was: upload the load profile, that would make sense, here is your quote. Today the customer says: I want everything from you. We now cover much, much more.”

03 · The product innovation

Products that did not exist before

At SEINE, the effect of minimum shows in the product range itself. The storage system supplier has become a provider that sells services it previously could not calculate.

The holistic energy project

Where a storage system used to be quoted, today there is a project: storage system, AC connection, SEINE OS, civil engineering, certification, the planning process with the grid operator. Because scenarios can be calculated against each other, grid expansion also becomes a decision question: the smaller storage system that fits the existing distribution board, against the larger one that needs a second distribution board but earns more.

For industrial customers, SEINE estimates this means around 50% more order volume, because extensions to existing infrastructure and protection and control concepts become part of the order.

"In existing sites, with industrial customers, the 50% more is right. Extensions and existing infrastructure account for a huge share, the protection and control concept alone."

– Jan Sievert, Technical Director

The expansion path

More and more customers come with a goal instead of an enquiry: climate neutral by 2035. Instead of selling them one large storage system, SEINE calculates the way there in steps. Today 1 MW of power and 2 MWh of capacity, in the next stage more, designed so that the first step fits the second. One quote becomes multi-year support.

Procurement optimisation

The newest product has only an indirect connection to hardware. SEINE OS has always been able to control procurement optimisation. What is new is the advice on it: SEINE calculates electricity procurement for customers, not 100% spot or 100% fixed price, but the optimal share, including PPA and electricity supply models. Energy consulting that a storage system manufacturer could not offer like this before.

"We also look at procurement. Not simply 100% spot or 100% fixed, but also with PPAs. And we tell the customer what the perfect share would be for them."

– Johannes Rosenthal, Business Development ESS

Competitor comparison as a consulting service

Industrial customers enquire with several providers in parallel. Often there is a quote on the table: similar storage capacity, cheaper, "without operating costs", because the provider only optimises self-consumption. The customer's question is then always the same: Why are you more expensive?

Today SEINE recalculates both quotes in minimum. The control system costs the customer on an ongoing basis, but in Multi-Use it saves many times that.

"Then the customer no longer sees our control system as an ongoing cost item. They see: we spend €10,000 a year and save another €50,000 a year on top. That can really only be shown with minimum. Otherwise we would have to tell the customer some story."

– Johannes Rosenthal, Business Development ESS

This is the CAPEX-OPEX tension that shapes the whole energy transition: operating costs become investments, and the investment only pays off if the ongoing effects are proven. SEINE can provide that proof today, even against competitors who claim that a storage system is a storage system. SEINE's approach: explain instead of claim.

New contacts

With the new products, the people across the table have changed too. Whoever used to talk storage sizes with the technical director now sits down with the energy buyer and the site manager. "These days it is always energy buyers, site managers or technical directors on our side," says Jan Sievert. A storage system manufacturer that talks to energy purchasing about PPA shares is no longer selling a product, but a service.

04 · The proof

One kilowatt off reality

Depth is only a selling point if it holds up. The strongest evidence came from operation. A customer with a 6.3 MW load peak has been running a SEINE storage system in atypical grid usage since spring. They wanted to know how good SEINE really is, and had someone check where the real-world peak shaving lay compared with the minimum design.

"This is my favourite comparison when customers ask how good minimum actually is. We were one kilowatt off the design. That alone shows how good the tool is."

– Johannes Rosenthal, Business Development ESS

Johannes puts this in honest context: so far it was the only systematic comparison, because day to day there is no capacity for it. That is exactly why it carries weight, as the customer initiated the test, not SEINE.

Quite a lot has now been completed or is under way. The first projects designed with minimum went online in early 2026. Today seven large-scale storage projects are running, around 30 storage projects in total with about 25 MWh of capacity, all designed with minimum. Storage projects have long lead times, and MiSpeL (German BNetzA rules for storage that charges both grid power and on-site renewable power) registration and grid applications take their time. By the end of 2026 SEINE expects 35 to 40 running projects.

The systems currently run in self-consumption optimisation and peak shaving, one or two already in atypical grid usage. And the big levers are still to come: the new grid fee systems and MiSpeL. "Very few control systems on the market can model that at all," says Jan.

SEINE does not quote a firm conversion rate, because storage prices have fallen too sharply in two years. The direction is still clear, as Jan puts it:

"Before, we were very professional on the technical side. Now we are on the energy market side too. In some projects that led to the decision for us. Above all it builds trust, and that has a correspondingly positive effect on the conversion rate: more quality instead of quantity."

– Jan Sievert, Technical Director

Because every cost item is in the potential analysis, the customer knows that nothing more will come their way. "What we have in black and white also happens that way later." With industrial customers, that is what decides it in the end: a hard-nosed comparison of figures, data and facts that holds up in operation.

05 · Today

The customer concentrates on their core business

"We want to support mid-sized companies and industry from an energy market and technical perspective so that they can concentrate on their production and core business. And we take care of all energy market and energy cost topics."

– Jan Sievert, Technical Director, SEINE Batteriesysteme

This is no longer a manufacturer's promise, but the service promise of an energy service provider. It works in a market where many providers sell on price and with isolated solutions. "We don't want to compete there, we want to go where it gets difficult," says Johannes. "Our market is the best-bidder market." The positioning only holds if the customer can calculate the difference between cheap and better. That is exactly what depth in energy market terms delivers.

Asked what would happen if minimum were switched off tomorrow, there is no move to another tool:

"Then we would probably try to implement it ourselves. There is nothing on the market that can currently model this."

– Johannes Rosenthal, Business Development ESS, SEINE Batteriesysteme

From minimum's point of view, SEINE is one of the three most intensive users among around 80 customers. Most users use 20 to 30% of the calculation depth, SEINE is at 70 to 80%. Because the team sells products that would not exist without this depth.

Ready for quotes that really hold up?

Bring an example project with you. In 30 minutes, we will show you how minimum energy transforms your pre-sales process.